Qline (Qpoint Phase II) R010 construction progress

The register lists Qline (Qpoint Phase II) R010 in Liwan1 as complete, with a registered completion date of February 2018. Its last site inspection on record was in February 2018. The developer is Al Mazaya Emirates Real Estate Development.

100%

Built, at the site inspection of 22 February 2018

Construction complete

Registered completion date
February 2018
Construction started
August 2016
First registered
May 2017
Developer
Al Mazaya Emirates Real Estate Development
Community
Liwan1
Units
154
Escrow bank
Mashreq Bank
Name in Arabic
كيولاين ( كيوبوينت فيز 2) R010
Project number
1905
Site inspections
3

Schedule

The register lists Qline (Qpoint Phase II) R010 as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20172018
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

22 February 2018

100%+2.9 pts

  • Qline (Qpoint Phase II) R010 construction site, inspection photo 1, 22 February 2018
  • Qline (Qpoint Phase II) R010 construction site, inspection photo 2, 22 February 2018
  • Qline (Qpoint Phase II) R010 construction site, inspection photo 3, 22 February 2018
  • Qline (Qpoint Phase II) R010 construction site, inspection photo 4, 22 February 2018

20 December 2017

97%+40 pts

  • Qline (Qpoint Phase II) R010 construction site, inspection photo 1, 20 December 2017
  • Qline (Qpoint Phase II) R010 construction site, inspection photo 2, 20 December 2017
  • Qline (Qpoint Phase II) R010 construction site, inspection photo 3, 20 December 2017
  • Qline (Qpoint Phase II) R010 construction site, inspection photo 4, 20 December 2017

9 August 2017

57%

  • Qline (Qpoint Phase II) R010 construction site, inspection photo 1, 9 August 2017
  • Qline (Qpoint Phase II) R010 construction site, inspection photo 2, 9 August 2017
  • Qline (Qpoint Phase II) R010 construction site, inspection photo 3, 9 August 2017
  • Qline (Qpoint Phase II) R010 construction site, inspection photo 4, 9 August 2017

All 30 site photos, by inspection date

Context

Liwan1 has 6 projects under construction, 28% built on average.

Own a unit in Qline (Qpoint Phase II) R010?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Qline (Qpoint Phase II) R010 handover date?
Construction of Qline (Qpoint Phase II) R010 is recorded as complete, with a registered completion date of February 2018. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Qline (Qpoint Phase II) R010?
Qline (Qpoint Phase II) R010 was 100% built at the site inspection on 22 February 2018. The site has been inspected 3 times since August 2017. The Land Department took 30 site photos at its inspections.
Is Qline (Qpoint Phase II) R010 delayed?
The register lists construction as complete.
Who is building Qline (Qpoint Phase II) R010?
The registered developer is Al Mazaya Emirates Real Estate Development.
Which bank holds the escrow account for Qline (Qpoint Phase II) R010?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.