Q - Zone (Qpoint - Phase III) Mu007 construction progress

The register lists Q - Zone (Qpoint - Phase III) Mu007 in Liwan1 as complete, with a registered completion date of June 2019. Its last site inspection on record was in June 2019. The developer is Altelal Alkhadraa Real Estate Development.

100%

Built, at the site inspection of 24 June 2019

Construction complete

Registered completion date
June 2019
Construction started
February 2018
First registered
June 2019
Developer
Altelal Alkhadraa Real Estate Development
Community
Liwan1
Units
176
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
كيوزون (كيوبوينت فيز 3) Mu007
Project number
2095
Site inspections
2

Schedule

The register lists Q - Zone (Qpoint - Phase III) Mu007 as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2019
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

24 June 2019

100%+29 pts

  • Q - Zone (Qpoint - Phase III) Mu007 construction site, inspection photo 1, 24 June 2019
  • Q - Zone (Qpoint - Phase III) Mu007 construction site, inspection photo 2, 24 June 2019
  • Q - Zone (Qpoint - Phase III) Mu007 construction site, inspection photo 3, 24 June 2019
  • Q - Zone (Qpoint - Phase III) Mu007 construction site, inspection photo 4, 24 June 2019

15 January 2019

71%

  • Q - Zone (Qpoint - Phase III) Mu007 construction site, inspection photo 1, 15 January 2019
  • Q - Zone (Qpoint - Phase III) Mu007 construction site, inspection photo 2, 15 January 2019
  • Q - Zone (Qpoint - Phase III) Mu007 construction site, inspection photo 3, 15 January 2019
  • Q - Zone (Qpoint - Phase III) Mu007 construction site, inspection photo 4, 15 January 2019

All 23 site photos, by inspection date

Context

Liwan1 has 6 projects under construction, 28% built on average.

Own a unit in Q - Zone (Qpoint - Phase III) Mu007?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Q - Zone (Qpoint - Phase III) Mu007 handover date?
Construction of Q - Zone (Qpoint - Phase III) Mu007 is recorded as complete, with a registered completion date of June 2019. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Q - Zone (Qpoint - Phase III) Mu007?
Q - Zone (Qpoint - Phase III) Mu007 was 100% built at the site inspection on 24 June 2019. The site has been inspected 2 times since January 2019. The Land Department took 23 site photos at its inspections.
Is Q - Zone (Qpoint - Phase III) Mu007 delayed?
The register lists construction as complete.
Who is building Q - Zone (Qpoint - Phase III) Mu007?
The registered developer is Altelal Alkhadraa Real Estate Development.
Which bank holds the escrow account for Q - Zone (Qpoint - Phase III) Mu007?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.