The Residences construction progress
The register lists The Residences in Jumeirah Lakes Towers as complete, with a registered completion date of July 2019. Its last site inspection on record was in September 2019. The developer is Signature D T Real Estate Development.
100%
Built, at the site inspection of 9 September 2019
Construction complete
- Registered completion date
- July 2019
- Construction started
- January 2015
- First registered
- September 2016
- Developer
- Signature D T Real Estate Development
- Community
- Jumeirah Lakes Towers
- Units
- 82
- Escrow bank
- The National Bank of Fujairah
- Name in Arabic
- المنازل
- Project number
- 1758
- Site inspections
- 8
Schedule
The register lists The Residences as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.
Site inspections
9 September 2019
100%+4.7 pts
1 May 2019
95%+8.1 pts
12 December 2018
87%+11 pts
26 July 2018
77%+11 pts
11 March 2018
65%+10 pts
13 November 2017
55%+13 pts
24 July 2017
42%+18 pts
1 March 2017
24%
Context
Jumeirah Lakes Towers has 8 projects under construction, 51% built on average.
Own a unit in The Residences?
The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.
Notify me when it launchesQuestions
- When is the The Residences handover date?
- Construction of The Residences is recorded as complete, with a registered completion date of July 2019. Handover of individual units follows on the developer's schedule, which the register does not show.
- What is the latest construction update on The Residences?
- The Residences was 100% built at the site inspection on 9 September 2019. The site has been inspected 8 times since March 2017. The Land Department took 83 site photos at its inspections.
- Is The Residences delayed?
- The register lists construction as complete.
- Who is building The Residences?
- The registered developer is Signature D T Real Estate Development.
- Which bank holds the escrow account for The Residences?
- The National Bank of Fujairah. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Vue Du LacNearby in Jumeirah Lakes Towers. 0%, Due December 2026.
- Viewz 1 By DanubeNearby in Jumeirah Lakes Towers. 66%, Due June 2026, passed.
- Viewz 2 By DanubeNearby in Jumeirah Lakes Towers. 65%, Due June 2026, passed.
- Verde By SobhaNearby in Jumeirah Lakes Towers. 85%, Due June 2027.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.