Serenia District - West construction progress
Serenia District - West in Jumeirah Islands is 2.8% built at the Land Department inspection of May 2026. Developer Palma Homes Real Estate Development. Completion registered for December 2028.
2.8%
Built, at the Land Department site inspection of 11 May 2026
Running behind its date
- Completion date (Land Department)
- December 2028
- Finish at recent pace
- December 2045
- Construction started
- January 2025
- Registered with the Land Department
- February 2025
- Developer
- Palma Homes Real Estate Development
- Community
- Jumeirah Islands
- Units
- 423
- Escrow bank
- Sharjah Islamic Bank
- Name in Arabic
- سيرينيا ديستريكت - ويست
- Land Department project number
- 3408
- Land Department site inspections
- 4
Schedule
Between October 2025 and May 2026 the site added about 0.4 points a month. At that rate it would finish around December 2045, more than three months after the December 2028 date registered with the Land Department.
Site inspections
11 May 2026
2.8%+2.5 pts
28 January 2026
0.4%+0.3 pts
21 October 2025
0.1%+0.1 pts
5 February 2025
0%
Context
Jumeirah Islands has 11 projects under construction, 43% built on average.
Palma Homes Real Estate Development has 2 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Serenia District - West?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Serenia District - West be completed?
- The completion date registered with the Dubai Land Department is December 2028. At the pace of its recent inspections the site would reach 100% around December 2045. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Serenia District - West is built?
- 2.8%, measured at the Land Department site inspection on 11 May 2026. The Land Department engineers have inspected the site 4 times since February 2025.
- Is Serenia District - West delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2028.
- Who is building Serenia District - West?
- The registered developer is Palma Homes Real Estate Development. It has 1 other project under construction in Dubai.
- Which bank holds the escrow account for Serenia District - West?
- Sharjah Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Serenia District - EastAlso by Palma Homes Real Estate Development. 1.1%, Due June 2030.
- The Wind Tower INearby in Jumeirah Islands. 75%, Due June 2023, passed.
- The Wind Tower IiNearby in Jumeirah Islands. 85%, Due June 2023, passed.
- Jumeirah Heights FrondsNearby in Jumeirah Islands. 32%, Due January 2013, passed.
- Seven City JltNearby in Jumeirah Islands. 28%, Due November 2025, passed.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.




.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)