Serenia District - West construction progress

The registered completion date for Serenia District - West in Jumeirah Islands is December 2028. At the last site inspection, in May 2026, it was 2.8% built. The developer is Palma Homes Real Estate Development.

2.8%

Built, at the site inspection of 11 May 2026

Running behind its date

Registered completion date
December 2028
Finish at recent pace
December 2045
Construction started
January 2025
First registered
February 2025
Developer
Palma Homes Real Estate Development
Units
423
Escrow bank
Sharjah Islamic Bank
Name in Arabic
سيرينيا ديستريكت - ويست
Project number
3408
Site inspections
4

Schedule

Between October 2025 and May 2026 the site added about 0.4 points a month. At that rate it would finish around December 2045, more than three months after its registered date of December 2028.

0%25%50%75%100%202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

11 May 2026

2.8%+2.5 pts

  • Serenia District - West construction site, inspection photo 1, 11 May 2026
  • Serenia District - West construction site, inspection photo 2, 11 May 2026
  • Serenia District - West construction site, inspection photo 3, 11 May 2026
  • Serenia District - West construction site, inspection photo 4, 11 May 2026

28 January 2026

0.4%+0.3 pts

  • Serenia District - West construction site, inspection photo 1, 28 January 2026
  • Serenia District - West construction site, inspection photo 2, 28 January 2026
  • Serenia District - West construction site, inspection photo 3, 28 January 2026
  • Serenia District - West construction site, inspection photo 4, 28 January 2026

21 October 2025

0.1%+0.1 pts

  • Serenia District - West construction site, inspection photo 1, 21 October 2025
  • Serenia District - West construction site, inspection photo 2, 21 October 2025

5 February 2025

0%

  • Serenia District - West construction site, inspection photo 1, 5 February 2025
  • Serenia District - West construction site, inspection photo 2, 5 February 2025
  • Serenia District - West construction site, inspection photo 3, 5 February 2025

All 15 site photos, by inspection date

Context

Jumeirah Islands has 11 projects under construction, 45% built on average.

Palma Homes Real Estate Development has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Serenia District - West?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Serenia District - West handover date?
The registered completion date is December 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around December 2045. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Serenia District - West?
Serenia District - West was 2.8% built at the site inspection on 11 May 2026. The site has been inspected 4 times since February 2025. The Land Department took 15 site photos at its inspections.
Is Serenia District - West delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2028.
Who is building Serenia District - West?
The registered developer is Palma Homes Real Estate Development. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Serenia District - West?
Sharjah Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.