Mbl Signature construction progress
The registered completion date for Mbl Signature in Jumeirah Islands is March 2027. At the last site inspection, in November 2026, it was 80% built. The developer is Mag 10 Property Development Dmcc.
80%
Built, at the site inspection of 10 November 2026
On pace for its date
- Registered completion date
- March 2027
- Finish at recent pace
- May 2027
- Construction started
- May 2025
- First registered
- June 2025
- Developer
- Mag 10 Property Development Dmcc
- Community
- Jumeirah Islands
- Units
- 463
- Escrow bank
- Abu Dhabi Commercial Bank
- Name in Arabic
- ام بي ال سيجنتشر
- Project number
- 3780
- Site inspections
- 4
Schedule
Since December 2025 Mbl Signature has added about 3.5 points a month. That puts 100% around May 2027, within three months of its registered completion date of March 2027.
Site inspections
10 November 2026
80%+20 pts
6 May 2026
60%+17 pts
24 December 2025
43%+7.7 pts
11 June 2025
35%
Context
Jumeirah Islands has 11 projects under construction, 45% built on average.
Own a unit in Mbl Signature?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Mbl Signature handover date?
- The registered completion date is March 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around May 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Mbl Signature?
- Mbl Signature was 80% built at the site inspection on 10 November 2026. The site has been inspected 4 times since June 2025. The Land Department took 50 site photos at its inspections.
- Is Mbl Signature delayed?
- Not on current figures. At the rate of the last year it finishes within three months of its registered date of March 2027.
- Who is building Mbl Signature?
- The registered developer is Mag 10 Property Development Dmcc.
- Which bank holds the escrow account for Mbl Signature?
- Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- The Wind Tower INearby in Jumeirah Islands. 75%, Due June 2023, passed.
- The Wind Tower IINearby in Jumeirah Islands. 85%, Due June 2023, passed.
- Jumeirah Heights FrondsNearby in Jumeirah Islands. 32%, Due January 2013, passed.
- Seven City JltNearby in Jumeirah Islands. 28%, Due November 2025, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.

.jpeg&w=3840&q=75)








.jpeg&w=3840&q=75)