Skip to content

Eltiera Heights construction progress

The registered completion date for Eltiera Heights in Jumeirah Islands is December 2028. At the last site inspection, in July 2026, it was 3.0% built. The developer is Ellington Pcfc Developers.

3.0%

Built, at the site inspection of 20 July 2026

Running behind its date

Registered completion date
December 2028
Finish at recent pace
May 2039
Construction started
June 2025
First registered
September 2025
Developer
Ellington Pcfc Developers
Units
357
Escrow bank
National Bank of Ras Al Khaimah
Name in Arabic
إلتييرا هايتس
Project number
3852
Site inspections
3

Schedule

Between March 2026 and July 2026 the site added about 0.6 points a month. At that rate it would finish around May 2039, more than three months after its registered date of December 2028.

0%25%50%75%100%202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

20 July 2026

3.0%+2.7 pts

  • Eltiera Heights construction site, inspection photo 1, 20 July 2026
  • Eltiera Heights construction site, inspection photo 2, 20 July 2026
  • Eltiera Heights construction site, inspection photo 3, 20 July 2026
  • Eltiera Heights construction site, inspection photo 4, 20 July 2026

13 March 2026

0.3%+0.3 pts

  • Eltiera Heights construction site, inspection photo 1, 13 March 2026
  • Eltiera Heights construction site, inspection photo 2, 13 March 2026
  • Eltiera Heights construction site, inspection photo 3, 13 March 2026

2 July 2025

0%

  • Eltiera Heights construction site, inspection photo 1, 2 July 2025
  • Eltiera Heights construction site, inspection photo 2, 2 July 2025

All 10 site photos, by inspection date

Context

Jumeirah Islands has 11 projects under construction, 45% built on average.

Ellington Pcfc Developers has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Eltiera Heights?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Eltiera Heights handover date?
The registered completion date is December 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around May 2039. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Eltiera Heights?
Eltiera Heights was 3.0% built at the site inspection on 20 July 2026. The site has been inspected 3 times since July 2025. The Land Department took 10 site photos at its inspections.
Is Eltiera Heights delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2028.
Who is building Eltiera Heights?
The registered developer is Ellington Pcfc Developers. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Eltiera Heights?
National Bank of Ras Al Khaimah. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.