Montage construction photos

37 photos taken by Dubai Land Department engineers at 8 site inspections, newest first. The percentage is how much of Montage was built on the day of each visit.

6 August 202631% built

3 June 202624% built

16 February 202616% built

22 December 202512% built

4 November 20258.8% built

29 April 20252.5% built

25 December 20240% built

15 August 20240% built

Back to Montage construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.