Skip to content

Sorrento construction progress

The registered completion date for Sorrento is January 2030. At the last site inspection, in September 2026, it was 0.3% built. The developer is Island Oasis Properties.

0.3%

Built, at the site inspection of 8 September 2026

Running behind its date

Registered completion date
January 2030
Finish at recent pace
August 2262
Construction started
July 2026
First registered
March 2026
Units
754
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
سورينتو
Project number
4381
Site inspections
2

Schedule

Between February 2026 and September 2026 the site added about 0.0 points a month. At that rate it would finish around August 2262, more than three months after its registered date of January 2030.

0%25%50%75%100%2027202820292030
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

8 September 2026

0.3%+0.3 pts

  • Sorrento construction site, inspection photo 1, 8 September 2026
  • Sorrento construction site, inspection photo 2, 8 September 2026
  • Sorrento construction site, inspection photo 3, 8 September 2026

4 February 2026

0%

  • Sorrento construction site, inspection photo 1, 4 February 2026
  • Sorrento construction site, inspection photo 2, 4 February 2026

All 5 site photos, by inspection date

Context

Island Oasis Properties has 26 projects under construction in Dubai; 7 have passed their registered completion date.

Own a unit in Sorrento?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Sorrento handover date?
The registered completion date is January 2030. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around August 2262. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Sorrento?
Sorrento was 0.3% built at the site inspection on 8 September 2026. The site has been inspected 2 times since February 2026. The Land Department took 5 site photos at its inspections.
Is Sorrento delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of January 2030.
Who is building Sorrento?
The registered developer is Island Oasis Properties. It has 25 other projects under construction in Dubai.
Which bank holds the escrow account for Sorrento?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.