Shahrukhz By Danube construction progress

The registered completion date for Shahrukhz By Danube is June 2029. At the last site inspection, in August 2026, it was 1.9% built. The developer is Danube Properties Development.

1.9%

Built, at the site inspection of 13 August 2026

Running behind its date

Registered completion date
June 2029
Finish at recent pace
May 2069
Construction started
January 2026
First registered
November 2025
Units
662
Escrow bank
First Abu Dhabi Bank
Name in Arabic
شاروخز من دانوب
Project number
4166
Site inspections
3

Schedule

Between October 2025 and August 2026 the site added about 0.2 points a month. At that rate it would finish around May 2069, more than three months after its registered date of June 2029.

0%25%50%75%100%2026202720282029
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

13 August 2026

1.9%+0.6 pts

  • Shahrukhz By Danube construction site, inspection photo 1, 13 August 2026
  • Shahrukhz By Danube construction site, inspection photo 2, 13 August 2026
  • Shahrukhz By Danube construction site, inspection photo 3, 13 August 2026

24 April 2026

1.2%+1.2 pts

  • Shahrukhz By Danube construction site, inspection photo 1, 24 April 2026
  • Shahrukhz By Danube construction site, inspection photo 2, 24 April 2026
  • Shahrukhz By Danube construction site, inspection photo 3, 24 April 2026
  • Shahrukhz By Danube construction site, inspection photo 4, 24 April 2026

21 October 2025

0%

  • Shahrukhz By Danube construction site, inspection photo 1, 21 October 2025
  • Shahrukhz By Danube construction site, inspection photo 2, 21 October 2025

All 9 site photos, by inspection date

Context

Danube Properties Development has 23 projects under construction in Dubai; 4 have passed their registered completion date.

Own a unit in Shahrukhz By Danube?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Shahrukhz By Danube handover date?
The registered completion date is June 2029. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around May 2069. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Shahrukhz By Danube?
Shahrukhz By Danube was 1.9% built at the site inspection on 13 August 2026. The site has been inspected 3 times since October 2025. The Land Department took 9 site photos at its inspections.
Is Shahrukhz By Danube delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2029.
Who is building Shahrukhz By Danube?
The registered developer is Danube Properties Development. It has 22 other projects under construction in Dubai.
Which bank holds the escrow account for Shahrukhz By Danube?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.