Shahrukhz By Danube construction progress

Shahrukhz By Danube is 1.9% built at the Land Department inspection of August 2026. Developer Danube Properties Development. Completion registered for June 2029.

1.9%

Built, at the Land Department site inspection of 13 August 2026

Running behind its date

Completion date (Land Department)
June 2029
Finish at recent pace
May 2069
Construction started
January 2026
Registered with the Land Department
November 2025
Units
662
Escrow bank
First Abu Dhabi Bank
Name in Arabic
شاروخز من دانوب
Land Department project number
4166
Land Department site inspections
3

Schedule

Between October 2025 and August 2026 the site added about 0.2 points a month. At that rate it would finish around May 2069, more than three months after the June 2029 date registered with the Land Department.

0%25%50%75%100%2026202720282029
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

13 August 2026

1.9%+0.6 pts

  • Shahrukhz By Danube construction site, Land Department inspection photo 1, 13 August 2026
  • Shahrukhz By Danube construction site, Land Department inspection photo 2, 13 August 2026
  • Shahrukhz By Danube construction site, Land Department inspection photo 3, 13 August 2026

24 April 2026

1.2%+1.2 pts

  • Shahrukhz By Danube construction site, Land Department inspection photo 1, 24 April 2026
  • Shahrukhz By Danube construction site, Land Department inspection photo 2, 24 April 2026
  • Shahrukhz By Danube construction site, Land Department inspection photo 3, 24 April 2026
  • Shahrukhz By Danube construction site, Land Department inspection photo 4, 24 April 2026

21 October 2025

0%

  • Shahrukhz By Danube construction site, Land Department inspection photo 1, 21 October 2025
  • Shahrukhz By Danube construction site, Land Department inspection photo 2, 21 October 2025

All 9 site photos, by inspection date

Context

Danube Properties Development has 23 projects under construction in Dubai; 4 have passed their registered completion date.

Own a unit in Shahrukhz By Danube?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Shahrukhz By Danube be completed?
The completion date registered with the Dubai Land Department is June 2029. At the pace of its recent inspections the site would reach 100% around May 2069. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Shahrukhz By Danube is built?
1.9%, measured at the Land Department site inspection on 13 August 2026. The Land Department engineers have inspected the site 3 times since October 2025.
Is Shahrukhz By Danube delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2029.
Who is building Shahrukhz By Danube?
The registered developer is Danube Properties Development. It has 22 other projects under construction in Dubai.
Which bank holds the escrow account for Shahrukhz By Danube?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.