Skip to content

Serenz By Danube construction progress

Serenz By Danube is 0.1% built at the Land Department inspection of July 2026. Developer Danube Properties Development. Completion registered for December 2029.

0.1%

Built, at the Land Department site inspection of 15 July 2026

Running behind its date

Completion date (Land Department)
December 2029
Finish at recent pace
August 2597
Construction started
May 2026
Registered with the Land Department
February 2026
Units
1,227
Escrow bank
Commercial Bank of Dubai
Name in Arabic
سيرنز من دانوب
Land Department project number
4338
Land Department site inspections
2

Schedule

Between January 2026 and July 2026 the site added about 0.0 points a month. At that rate it would finish around August 2597, more than three months after the December 2029 date registered with the Land Department.

0%25%50%75%100%202720282029
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

15 July 2026

0.1%+0.1 pts

  • Serenz By Danube construction site, Land Department inspection photo 1, 15 July 2026
  • Serenz By Danube construction site, Land Department inspection photo 2, 15 July 2026
  • Serenz By Danube construction site, Land Department inspection photo 3, 15 July 2026
  • Serenz By Danube construction site, Land Department inspection photo 4, 15 July 2026

29 January 2026

0%

  • Serenz By Danube construction site, Land Department inspection photo 1, 29 January 2026
  • Serenz By Danube construction site, Land Department inspection photo 2, 29 January 2026

All 7 site photos, by inspection date

Context

Danube Properties Development has 23 projects under construction in Dubai; 4 have passed their registered completion date.

Own a unit in Serenz By Danube?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Serenz By Danube be completed?
The completion date registered with the Dubai Land Department is December 2029. At the pace of its recent inspections the site would reach 100% around August 2597. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Serenz By Danube is built?
0.1%, measured at the Land Department site inspection on 15 July 2026. The Land Department engineers have inspected the site 2 times since January 2026.
Is Serenz By Danube delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2029.
Who is building Serenz By Danube?
The registered developer is Danube Properties Development. It has 22 other projects under construction in Dubai.
Which bank holds the escrow account for Serenz By Danube?
Commercial Bank of Dubai. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.