Piazza Roma construction progress

The registered completion date for Piazza Roma is June 2030. At the last site inspection, in August 2026, it was 0.2% built. The developer is Island Oasis Properties.

0.2%

Built, at the site inspection of 18 August 2026

Running behind its date

Registered completion date
June 2030
Finish at recent pace
May 2294
Construction started
July 2026
First registered
February 2026
Units
336
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
بياتسا روما
Project number
4379
Site inspections
2

Schedule

Between February 2026 and August 2026 the site added about 0.0 points a month. At that rate it would finish around May 2294, more than three months after its registered date of June 2030.

0%25%50%75%100%2027202820292030
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

18 August 2026

0.2%+0.2 pts

  • Piazza Roma construction site, inspection photo 1, 18 August 2026
  • Piazza Roma construction site, inspection photo 2, 18 August 2026
  • Piazza Roma construction site, inspection photo 3, 18 August 2026

3 February 2026

0%

  • Piazza Roma construction site, inspection photo 1, 3 February 2026
  • Piazza Roma construction site, inspection photo 2, 3 February 2026

All 5 site photos, by inspection date

Context

Island Oasis Properties has 26 projects under construction in Dubai; 7 have passed their registered completion date.

Own a unit in Piazza Roma?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Piazza Roma handover date?
The registered completion date is June 2030. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around May 2294. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Piazza Roma?
Piazza Roma was 0.2% built at the site inspection on 18 August 2026. The site has been inspected 2 times since February 2026. The Land Department took 5 site photos at its inspections.
Is Piazza Roma delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2030.
Who is building Piazza Roma?
The registered developer is Island Oasis Properties. It has 25 other projects under construction in Dubai.
Which bank holds the escrow account for Piazza Roma?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.