Piazza Roma construction progress
The registered completion date for Piazza Roma is June 2030. At the last site inspection, in August 2026, it was 0.2% built. The developer is Island Oasis Properties.
0.2%
Built, at the site inspection of 18 August 2026
Running behind its date
- Registered completion date
- June 2030
- Finish at recent pace
- May 2294
- Construction started
- July 2026
- First registered
- February 2026
- Developer
- Island Oasis Properties
- Units
- 336
- Escrow bank
- Abu Dhabi Commercial Bank
- Name in Arabic
- بياتسا روما
- Project number
- 4379
- Site inspections
- 2
Schedule
Between February 2026 and August 2026 the site added about 0.0 points a month. At that rate it would finish around May 2294, more than three months after its registered date of June 2030.
Site inspections
18 August 2026
0.2%+0.2 pts
3 February 2026
0%
Context
Island Oasis Properties has 26 projects under construction in Dubai; 7 have passed their registered completion date.
Own a unit in Piazza Roma?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Piazza Roma handover date?
- The registered completion date is June 2030. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around May 2294. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Piazza Roma?
- Piazza Roma was 0.2% built at the site inspection on 18 August 2026. The site has been inspected 2 times since February 2026. The Land Department took 5 site photos at its inspections.
- Is Piazza Roma delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2030.
- Who is building Piazza Roma?
- The registered developer is Island Oasis Properties. It has 25 other projects under construction in Dubai.
- Which bank holds the escrow account for Piazza Roma?
- Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Damac Lagoons - Nice 1Also by Island Oasis Properties. 94%, Due July 2025, passed.
- Damac Lagoons - Nice 2Also by Island Oasis Properties. 84%, Due July 2025, passed.
- Damac Lagoons - Venice (1)Also by Island Oasis Properties. 74%, Due September 2025, passed.
- Damac Lagoons - IbizaAlso by Island Oasis Properties. 79%, Due December 2025, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.