Linea By Holm construction progress

The registered completion date for Linea By Holm is June 2028. At the last site inspection, in November 2026, it was 18% built. The developer is Holm Avenue Real Estate Development.

18%

Built, at the site inspection of 3 November 2026

Running behind its date

Registered completion date
June 2028
Finish at recent pace
July 2030
Construction started
February 2026
First registered
January 2026
Units
210
Escrow bank
Emirates NBD
Name in Arabic
لينيا باي هولم
Project number
4331
Site inspections
4

Schedule

Between January 2026 and November 2026 the site added about 1.9 points a month. At that rate it would finish around July 2030, more than three months after its registered date of June 2028.

0%25%50%75%100%20272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

3 November 2026

18%+17 pts

  • Linea By Holm construction site, inspection photo 1, 3 November 2026
  • Linea By Holm construction site, inspection photo 2, 3 November 2026
  • Linea By Holm construction site, inspection photo 3, 3 November 2026
  • Linea By Holm construction site, inspection photo 4, 3 November 2026

27 July 2026

0.7%+0.5 pts

  • Linea By Holm construction site, inspection photo 1, 27 July 2026
  • Linea By Holm construction site, inspection photo 2, 27 July 2026
  • Linea By Holm construction site, inspection photo 3, 27 July 2026
  • Linea By Holm construction site, inspection photo 4, 27 July 2026

7 May 2026

0.1%+0.1 pts

  • Linea By Holm construction site, inspection photo 1, 7 May 2026
  • Linea By Holm construction site, inspection photo 2, 7 May 2026
  • Linea By Holm construction site, inspection photo 3, 7 May 2026
  • Linea By Holm construction site, inspection photo 4, 7 May 2026

12 January 2026

0%

  • Linea By Holm construction site, inspection photo 1, 12 January 2026
  • Linea By Holm construction site, inspection photo 2, 12 January 2026

All 17 site photos, by inspection date

Context

Holm Avenue Real Estate Development has 3 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Linea By Holm?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Linea By Holm handover date?
The registered completion date is June 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around July 2030. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Linea By Holm?
Linea By Holm was 18% built at the site inspection on 3 November 2026. The site has been inspected 4 times since January 2026. The Land Department took 17 site photos at its inspections.
Is Linea By Holm delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2028.
Who is building Linea By Holm?
The registered developer is Holm Avenue Real Estate Development. It has 2 other projects under construction in Dubai.
Which bank holds the escrow account for Linea By Holm?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.