Holm One construction progress
Holm One is 6.8% built at the Land Department inspection of July 2026. Developer Holm Avenue Real Estate Development. Completion registered for March 2028.
6.8%
Built, at the Land Department site inspection of 27 July 2026
Running behind its date
- Completion date (Land Department)
- March 2028
- Finish at recent pace
- August 2036
- Construction started
- November 2025
- Registered with the Land Department
- November 2025
- Developer
- Holm Avenue Real Estate Development
- Units
- 218
- Escrow bank
- Emirates NBD
- Name in Arabic
- هولم وان
- Land Department project number
- 4181
- Land Department site inspections
- 3
Schedule
Between October 2025 and July 2026 the site added about 0.8 points a month. At that rate it would finish around August 2036, more than three months after the March 2028 date registered with the Land Department.
Site inspections
27 July 2026
6.8%+5.9 pts
13 March 2026
1.0%+1.0 pts
29 October 2025
0%
Context
Holm Avenue Real Estate Development has 2 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Holm One?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Holm One be completed?
- The completion date registered with the Dubai Land Department is March 2028. At the pace of its recent inspections the site would reach 100% around August 2036. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Holm One is built?
- 6.8%, measured at the Land Department site inspection on 27 July 2026. The Land Department engineers have inspected the site 3 times since October 2025.
- Is Holm One delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2028.
- Who is building Holm One?
- The registered developer is Holm Avenue Real Estate Development. It has 1 other project under construction in Dubai.
- Which bank holds the escrow account for Holm One?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.