Elaris Axis construction progress

The registered completion date for Elaris Axis is November 2028. At the last site inspection, in November 2026, it was 4.2% built. The developer is Object One Real Estate Development.

4.2%

Built, at the site inspection of 9 November 2026

Running behind its date

Registered completion date
November 2028
Finish at recent pace
October 2049
Construction started
January 2026
First registered
September 2026
Units
171
Escrow bank
Abu Dhabi Islamic Bank
Name in Arabic
ايلايرس اكسس
Project number
4212
Site inspections
3

Schedule

Between November 2025 and November 2026 the site added about 0.3 points a month. At that rate it would finish around October 2049, more than three months after its registered date of November 2028.

0%25%50%75%100%202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

9 November 2026

4.2%+2.0 pts

  • Elaris Axis construction site, inspection photo 1, 9 November 2026
  • Elaris Axis construction site, inspection photo 2, 9 November 2026
  • Elaris Axis construction site, inspection photo 3, 9 November 2026

12 October 2026

2.2%+2.2 pts

  • Elaris Axis construction site, inspection photo 1, 12 October 2026
  • Elaris Axis construction site, inspection photo 2, 12 October 2026
  • Elaris Axis construction site, inspection photo 3, 12 October 2026

11 November 2025

0%

  • Elaris Axis construction site, inspection photo 1, 11 November 2025
  • Elaris Axis construction site, inspection photo 2, 11 November 2025

All 8 site photos, by inspection date

Context

Object One Real Estate Development has 13 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Elaris Axis?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Elaris Axis handover date?
The registered completion date is November 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around October 2049. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Elaris Axis?
Elaris Axis was 4.2% built at the site inspection on 9 November 2026. The site has been inspected 3 times since November 2025. The Land Department took 8 site photos at its inspections.
Is Elaris Axis delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of November 2028.
Who is building Elaris Axis?
The registered developer is Object One Real Estate Development. It has 12 other projects under construction in Dubai.
Which bank holds the escrow account for Elaris Axis?
Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.