Cetara construction progress
Cetara is 0.3% built at the Land Department inspection of September 2026. Developer Island Oasis Properties. Completion registered for January 2030.
0.3%
Built, at the Land Department site inspection of 8 September 2026
Running behind its date
- Completion date (Land Department)
- January 2030
- Finish at recent pace
- August 2262
- Construction started
- July 2026
- Registered with the Land Department
- March 2026
- Developer
- Island Oasis Properties
- Units
- 618
- Escrow bank
- Abu Dhabi Commercial Bank
- Name in Arabic
- سيتارا
- Land Department project number
- 4382
- Land Department site inspections
- 2
Schedule
Between February 2026 and September 2026 the site added about 0.0 points a month. At that rate it would finish around August 2262, more than three months after the January 2030 date registered with the Land Department.
Site inspections
8 September 2026
0.3%+0.3 pts
4 February 2026
0%
Context
Island Oasis Properties has 27 projects under construction in Dubai; 6 have passed their registered completion date.
Own a unit in Cetara?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Cetara be completed?
- The completion date registered with the Dubai Land Department is January 2030. At the pace of its recent inspections the site would reach 100% around August 2262. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Cetara is built?
- 0.3%, measured at the Land Department site inspection on 8 September 2026. The Land Department engineers have inspected the site 2 times since February 2026.
- Is Cetara delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of January 2030.
- Who is building Cetara?
- The registered developer is Island Oasis Properties. It has 26 other projects under construction in Dubai.
- Which bank holds the escrow account for Cetara?
- Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Damac Lagoons - Nice 1Also by Island Oasis Properties. 94%, Due July 2025, passed.
- Damac Lagoons - Nice 2Also by Island Oasis Properties. 84%.
- Damac Lagoons - PortofinoAlso by Island Oasis Properties. 97%, Due June 2025, passed.
- Damac Lagoons - Venice (1)Also by Island Oasis Properties. 74%, Due September 2025, passed.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.



.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)