Windsor House construction progress
The registered completion date for Windsor House in Dubai South Residential District is July 2029. At the last site inspection, in June 2026, it was 3.1% built. The developer is Ellington Sb Development.
3.1%
Built, at the site inspection of 17 June 2026
Running behind its date
- Registered completion date
- July 2029
- Finish at recent pace
- July 2050
- Construction started
- December 2025
- First registered
- December 2025
- Developer
- Ellington Sb Development
- Community
- Dubai South Residential District
- Units
- 424
- Escrow bank
- Sharjah Islamic Bank
- Name in Arabic
- ويندسور هاوس
- Project number
- 4035
- Site inspections
- 2
Schedule
Between September 2025 and June 2026 the site added about 0.3 points a month. At that rate it would finish around July 2050, more than three months after its registered date of July 2029.
Site inspections
17 June 2026
3.1%+3.1 pts
10 September 2025
0%
Context
Dubai South Residential District has 37 projects under construction, 43% built on average.
Own a unit in Windsor House?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Windsor House handover date?
- The registered completion date is July 2029. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around July 2050. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Windsor House?
- Windsor House was 3.1% built at the site inspection on 17 June 2026. The site has been inspected 2 times since September 2025. The Land Department took 7 site photos at its inspections.
- Is Windsor House delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of July 2029.
- Who is building Windsor House?
- The registered developer is Ellington Sb Development.
- Which bank holds the escrow account for Windsor House?
- Sharjah Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- South Bay 1Nearby in Dubai South Residential District. 94%, Due March 2025, passed.
- South Bay 2Nearby in Dubai South Residential District. 94%, Due May 2026, passed.
- South Bay 3 PremiumNearby in Dubai South Residential District. 88%.
- South Bay 4 PremiumNearby in Dubai South Residential District. 86%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.