Windsor House construction progress

Windsor House in Dubai South Residential District is 3.1% built at the Land Department inspection of June 2026. Developer Ellington Sb Development. Completion registered for July 2029.

3.1%

Built, at the Land Department site inspection of 17 June 2026

Running behind its date

Completion date (Land Department)
July 2029
Finish at recent pace
July 2050
Construction started
December 2025
Registered with the Land Department
December 2025
Developer
Ellington Sb Development
Units
424
Escrow bank
Sharjah Islamic Bank
Name in Arabic
ويندسور هاوس
Land Department project number
4035
Land Department site inspections
2

Schedule

Between September 2025 and June 2026 the site added about 0.3 points a month. At that rate it would finish around July 2050, more than three months after the July 2029 date registered with the Land Department.

0%25%50%75%100%2026202720282029
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

17 June 2026

3.1%+3.1 pts

  • Windsor House construction site, Land Department inspection photo 1, 17 June 2026
  • Windsor House construction site, Land Department inspection photo 2, 17 June 2026
  • Windsor House construction site, Land Department inspection photo 3, 17 June 2026
  • Windsor House construction site, Land Department inspection photo 4, 17 June 2026

10 September 2025

0%

  • Windsor House construction site, Land Department inspection photo 1, 10 September 2025
  • Windsor House construction site, Land Department inspection photo 2, 10 September 2025

All 7 site photos, by inspection date

Context

Dubai South Residential District has 40 projects under construction, 40% built on average.

Own a unit in Windsor House?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Windsor House be completed?
The completion date registered with the Dubai Land Department is July 2029. At the pace of its recent inspections the site would reach 100% around July 2050. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Windsor House is built?
3.1%, measured at the Land Department site inspection on 17 June 2026. The Land Department engineers have inspected the site 2 times since September 2025.
Is Windsor House delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of July 2029.
Who is building Windsor House?
The registered developer is Ellington Sb Development.
Which bank holds the escrow account for Windsor House?
Sharjah Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.