Westar Altair construction progress
The registered completion date for Westar Altair in Dubai South Residential District is May 2027. At the last site inspection, in July 2026, it was 63% built. The developer is Westar Properties.
63%
Built, at the site inspection of 20 July 2026
On pace for its date
- Registered completion date
- May 2027
- Finish at recent pace
- March 2027
- Construction started
- March 2025
- First registered
- April 2025
- Developer
- Westar Properties
- Community
- Dubai South Residential District
- Units
- 56
- Escrow bank
- Emirates NBD
- Name in Arabic
- ويستار ألتير
- Project number
- 3515
- Site inspections
- 4
Schedule
Since August 2025 Westar Altair has added about 4.9 points a month. That puts 100% around March 2027, within three months of its registered completion date of May 2027.
Site inspections
20 July 2026
63%+23 pts
6 April 2026
40%+30 pts
29 August 2025
10%+10 pts
28 January 2025
0%
Context
Dubai South Residential District has 37 projects under construction, 43% built on average.
Own a unit in Westar Altair?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Westar Altair handover date?
- The registered completion date is May 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around March 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Westar Altair?
- Westar Altair was 63% built at the site inspection on 20 July 2026. The site has been inspected 4 times since January 2025. The Land Department took 22 site photos at its inspections.
- Is Westar Altair delayed?
- Not on current figures. At the rate of the last year it finishes within three months of its registered date of May 2027.
- Who is building Westar Altair?
- The registered developer is Westar Properties.
- Which bank holds the escrow account for Westar Altair?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- South Bay 1Nearby in Dubai South Residential District. 94%, Due March 2025, passed.
- South Bay 2Nearby in Dubai South Residential District. 94%, Due May 2026, passed.
- South Bay 3 PremiumNearby in Dubai South Residential District. 88%.
- South Bay 4 PremiumNearby in Dubai South Residential District. 86%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.
.jpeg&w=3840&q=75)