Westar Altair construction progress

The registered completion date for Westar Altair in Dubai South Residential District is May 2027. At the last site inspection, in July 2026, it was 63% built. The developer is Westar Properties.

63%

Built, at the site inspection of 20 July 2026

On pace for its date

Registered completion date
May 2027
Finish at recent pace
March 2027
Construction started
March 2025
First registered
April 2025
Developer
Westar Properties
Units
56
Escrow bank
Emirates NBD
Name in Arabic
ويستار ألتير
Project number
3515
Site inspections
4

Schedule

Since August 2025 Westar Altair has added about 4.9 points a month. That puts 100% around March 2027, within three months of its registered completion date of May 2027.

0%25%50%75%100%20262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

20 July 2026

63%+23 pts

  • Westar Altair construction site, inspection photo 1, 20 July 2026
  • Westar Altair construction site, inspection photo 2, 20 July 2026
  • Westar Altair construction site, inspection photo 3, 20 July 2026
  • Westar Altair construction site, inspection photo 4, 20 July 2026

6 April 2026

40%+30 pts

  • Westar Altair construction site, inspection photo 1, 6 April 2026
  • Westar Altair construction site, inspection photo 2, 6 April 2026
  • Westar Altair construction site, inspection photo 3, 6 April 2026
  • Westar Altair construction site, inspection photo 4, 6 April 2026

29 August 2025

10%+10 pts

  • Westar Altair construction site, inspection photo 1, 29 August 2025
  • Westar Altair construction site, inspection photo 2, 29 August 2025
  • Westar Altair construction site, inspection photo 3, 29 August 2025
  • Westar Altair construction site, inspection photo 4, 29 August 2025

28 January 2025

0%

  • Westar Altair construction site, inspection photo 1, 28 January 2025
  • Westar Altair construction site, inspection photo 2, 28 January 2025
  • Westar Altair construction site, inspection photo 3, 28 January 2025

All 22 site photos, by inspection date

Context

Dubai South Residential District has 37 projects under construction, 43% built on average.

Own a unit in Westar Altair?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Westar Altair handover date?
The registered completion date is May 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around March 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Westar Altair?
Westar Altair was 63% built at the site inspection on 20 July 2026. The site has been inspected 4 times since January 2025. The Land Department took 22 site photos at its inspections.
Is Westar Altair delayed?
Not on current figures. At the rate of the last year it finishes within three months of its registered date of May 2027.
Who is building Westar Altair?
The registered developer is Westar Properties.
Which bank holds the escrow account for Westar Altair?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.