The Serene construction progress

The Serene in Dubai South Residential District was registered to complete in October 2026 and is still under construction. At the last site inspection, in October 2026, it was 46% built. The developer is Al Mizan Serene Real Estate Development Dwc.

46%

Built, at the site inspection of 22 October 2026

2 months past its registered completion date

Registered completion date
October 2026
Finish at recent pace
September 2028
Construction started
April 2025
First registered
October 2025
Developer
Al Mizan Serene Real Estate Development Dwc
Units
106
Escrow bank
Bank of Baroda
Name in Arabic
ذي سيرين
Project number
4020
Site inspections
3

Schedule

The Serene was registered to complete in October 2026, 2 months ago, and is still under construction. Over the last year of inspections it has added about 2.4 points a month. Kept at that rate, the site would reach 100% around September 2028.

0%25%50%75%100%2026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

22 October 2026

46%+18 pts

  • The Serene construction site, inspection photo 1, 22 October 2026
  • The Serene construction site, inspection photo 2, 22 October 2026
  • The Serene construction site, inspection photo 3, 22 October 2026
  • The Serene construction site, inspection photo 4, 22 October 2026

4 March 2026

28%+18 pts

  • The Serene construction site, inspection photo 1, 4 March 2026
  • The Serene construction site, inspection photo 2, 4 March 2026
  • The Serene construction site, inspection photo 3, 4 March 2026
  • The Serene construction site, inspection photo 4, 4 March 2026

24 September 2025

10%

  • The Serene construction site, inspection photo 1, 24 September 2025
  • The Serene construction site, inspection photo 2, 24 September 2025
  • The Serene construction site, inspection photo 3, 24 September 2025
  • The Serene construction site, inspection photo 4, 24 September 2025

All 23 site photos, by inspection date

Context

Dubai South Residential District has 37 projects under construction, 43% built on average.

Own a unit in The Serene?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the The Serene handover date?
The registered completion date was October 2026, and the register still lists The Serene as under construction. At the pace of its recent inspections the site would reach 100% around September 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on The Serene?
The Serene was 46% built at the site inspection on 22 October 2026. The site has been inspected 3 times since September 2025. The Land Department took 23 site photos at its inspections.
Is The Serene delayed?
Yes. Its registered completion date of October 2026 has passed and the project is still listed as under construction.
Who is building The Serene?
The registered developer is Al Mizan Serene Real Estate Development Dwc.
Which bank holds the escrow account for The Serene?
Bank of Baroda. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.