The Serene construction progress

The Serene in Dubai South Residential District is 28% built at the Land Department inspection of March 2026. Developer Al Mizan Serene Real Estate Development Dwc. Completion registered for October 2026.

28%

Built, at the Land Department site inspection of 4 March 2026

0 months past its registered completion date

Completion date (Land Department)
October 2026
Finish at recent pace
December 2027
Construction started
April 2025
Registered with the Land Department
October 2025
Developer
Al Mizan Serene Real Estate Development Dwc
Units
106
Escrow bank
Bank of Baroda
Name in Arabic
ذي سيرين
Land Department project number
4020
Land Department site inspections
2

Schedule

The Serene was registered to complete in October 2026, 1 month ago, and is still under construction. Over the last year of inspections it has added about 3.4 points a month. Kept at that rate, the site would reach 100% around December 2027.

0%25%50%75%100%2026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

4 March 2026

28%+18 pts

  • The Serene construction site, Land Department inspection photo 1, 4 March 2026
  • The Serene construction site, Land Department inspection photo 2, 4 March 2026
  • The Serene construction site, Land Department inspection photo 3, 4 March 2026
  • The Serene construction site, Land Department inspection photo 4, 4 March 2026

24 September 2025

10%

  • The Serene construction site, Land Department inspection photo 1, 24 September 2025
  • The Serene construction site, Land Department inspection photo 2, 24 September 2025
  • The Serene construction site, Land Department inspection photo 3, 24 September 2025
  • The Serene construction site, Land Department inspection photo 4, 24 September 2025

All 10 site photos, by inspection date

Context

Dubai South Residential District has 40 projects under construction, 40% built on average. The Serene is behind that average.

Own a unit in The Serene?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Track the handover

Questions

When will The Serene be completed?
The completion date registered with the Dubai Land Department is October 2026. At the pace of its recent inspections the site would reach 100% around December 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of The Serene is built?
28%, measured at the Land Department site inspection on 4 March 2026. The Land Department engineers have inspected the site 2 times since September 2025.
Is The Serene delayed?
Yes. Its registered completion date of October 2026 has passed and the Land Department still lists it as under construction.
Who is building The Serene?
The registered developer is Al Mizan Serene Real Estate Development Dwc.
Which bank holds the escrow account for The Serene?
Bank of Baroda. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.