The Harmony construction progress

The register lists The Harmony in Dubai South Residential District as complete, with a registered completion date of October 2025. Its last site inspection on record was in October 2026. The developer is Al Mizan Harmony Development.

100%

Built, at the site inspection of 15 October 2026

Construction complete

Registered completion date
October 2025
Construction started
April 2024
First registered
August 2024
Developer
Al Mizan Harmony Development
Units
113
Escrow bank
Mashreq Bank
Name in Arabic
ذي هارموني
Project number
3130
Site inspections
6

Schedule

The register lists The Harmony as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

15 October 2026

98%+12 pts

  • The Harmony construction site, inspection photo 1, 15 October 2026
  • The Harmony construction site, inspection photo 2, 15 October 2026
  • The Harmony construction site, inspection photo 3, 15 October 2026
  • The Harmony construction site, inspection photo 4, 15 October 2026

23 June 2026

85%+22 pts

  • The Harmony construction site, inspection photo 1, 23 June 2026
  • The Harmony construction site, inspection photo 2, 23 June 2026
  • The Harmony construction site, inspection photo 3, 23 June 2026
  • The Harmony construction site, inspection photo 4, 23 June 2026

2 March 2026

63%+7.3 pts

  • The Harmony construction site, inspection photo 1, 2 March 2026
  • The Harmony construction site, inspection photo 2, 2 March 2026
  • The Harmony construction site, inspection photo 3, 2 March 2026
  • The Harmony construction site, inspection photo 4, 2 March 2026

6 November 2025

56%+16 pts

  • The Harmony construction site, inspection photo 1, 6 November 2025
  • The Harmony construction site, inspection photo 2, 6 November 2025
  • The Harmony construction site, inspection photo 3, 6 November 2025
  • The Harmony construction site, inspection photo 4, 6 November 2025

13 June 2025

40%+28 pts

  • The Harmony construction site, inspection photo 1, 13 June 2025
  • The Harmony construction site, inspection photo 2, 13 June 2025
  • The Harmony construction site, inspection photo 3, 13 June 2025
  • The Harmony construction site, inspection photo 4, 13 June 2025

13 June 2024

12%

  • The Harmony construction site, inspection photo 1, 13 June 2024
  • The Harmony construction site, inspection photo 2, 13 June 2024

All 38 site photos, by inspection date

Context

Dubai South Residential District has 37 projects under construction, 43% built on average.

Own a unit in The Harmony?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the The Harmony handover date?
Construction of The Harmony is recorded as complete, with a registered completion date of October 2025. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on The Harmony?
The Harmony was 100% built at the site inspection on 15 October 2026. The site has been inspected 6 times since June 2024. The Land Department took 38 site photos at its inspections.
Is The Harmony delayed?
The register lists construction as complete.
Who is building The Harmony?
The registered developer is Al Mizan Harmony Development.
Which bank holds the escrow account for The Harmony?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.