The Harmony construction progress

The Harmony in Dubai South Residential District is 85% built at the Land Department inspection of June 2026. Developer Al Mizan Harmony Development. Completion registered for October 2025.

85%

Built, at the Land Department site inspection of 23 June 2026

12 months past its registered completion date

Completion date (Land Department)
October 2025
Finish at recent pace
October 2026
Construction started
April 2024
Registered with the Land Department
August 2024
Developer
Al Mizan Harmony Development
Units
113
Escrow bank
Mashreq Bank
Name in Arabic
ذي هارموني
Land Department project number
3130
Land Department site inspections
5

Schedule

The Harmony was registered to complete in October 2025, 12 months ago, and is still under construction. Over the last year of inspections it has added about 3.9 points a month. Kept at that rate, the site would reach 100% around October 2026.

0%25%50%75%100%20252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

23 June 2026

85%+22 pts

  • The Harmony construction site, Land Department inspection photo 1, 23 June 2026
  • The Harmony construction site, Land Department inspection photo 2, 23 June 2026
  • The Harmony construction site, Land Department inspection photo 3, 23 June 2026
  • The Harmony construction site, Land Department inspection photo 4, 23 June 2026

2 March 2026

63%+7.3 pts

  • The Harmony construction site, Land Department inspection photo 1, 2 March 2026
  • The Harmony construction site, Land Department inspection photo 2, 2 March 2026
  • The Harmony construction site, Land Department inspection photo 3, 2 March 2026
  • The Harmony construction site, Land Department inspection photo 4, 2 March 2026

6 November 2025

56%+16 pts

  • The Harmony construction site, Land Department inspection photo 1, 6 November 2025
  • The Harmony construction site, Land Department inspection photo 2, 6 November 2025
  • The Harmony construction site, Land Department inspection photo 3, 6 November 2025
  • The Harmony construction site, Land Department inspection photo 4, 6 November 2025

13 June 2025

40%+28 pts

  • The Harmony construction site, Land Department inspection photo 1, 13 June 2025
  • The Harmony construction site, Land Department inspection photo 2, 13 June 2025
  • The Harmony construction site, Land Department inspection photo 3, 13 June 2025
  • The Harmony construction site, Land Department inspection photo 4, 13 June 2025

13 June 2024

12%

  • The Harmony construction site, Land Department inspection photo 1, 13 June 2024
  • The Harmony construction site, Land Department inspection photo 2, 13 June 2024

All 27 site photos, by inspection date

Context

Dubai South Residential District has 40 projects under construction, 40% built on average. The Harmony is ahead of that average.

Own a unit in The Harmony?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Track the handover

Questions

When will The Harmony be completed?
The completion date registered with the Dubai Land Department is October 2025. At the pace of its recent inspections the site would reach 100% around October 2026. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of The Harmony is built?
85%, measured at the Land Department site inspection on 23 June 2026. The Land Department engineers have inspected the site 5 times since June 2024.
Is The Harmony delayed?
Yes. Its registered completion date of October 2025 has passed and the Land Department still lists it as under construction.
Who is building The Harmony?
The registered developer is Al Mizan Harmony Development.
Which bank holds the escrow account for The Harmony?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.