The Collective construction progress
The registered completion date for The Collective in Dubai South Residential District is March 2028. At the last site inspection, in November 2026, it was 11% built. The developer is Bold Living Real Estate Development.
11%
Built, at the site inspection of 24 November 2026
Running behind its date
- Registered completion date
- March 2028
- Finish at recent pace
- January 2031
- Construction started
- August 2025
- First registered
- November 2025
- Developer
- Bold Living Real Estate Development
- Community
- Dubai South Residential District
- Units
- 94
- Escrow bank
- Emirates Islamic Bank
- Name in Arabic
- ذاكوليكتف
- Project number
- 3888
- Site inspections
- 3
Schedule
Between August 2026 and November 2026 the site added about 1.8 points a month. At that rate it would finish around January 2031, more than three months after its registered date of March 2028.
Site inspections
24 November 2026
11%+5.6 pts
20 August 2026
5.7%+5.7 pts
17 July 2025
0%
Context
Dubai South Residential District has 37 projects under construction, 43% built on average.
Own a unit in The Collective?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the The Collective handover date?
- The registered completion date is March 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around January 2031. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on The Collective?
- The Collective was 11% built at the site inspection on 24 November 2026. The site has been inspected 3 times since July 2025. The Land Department took 11 site photos at its inspections.
- Is The Collective delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2028.
- Who is building The Collective?
- The registered developer is Bold Living Real Estate Development.
- Which bank holds the escrow account for The Collective?
- Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- South Bay 1Nearby in Dubai South Residential District. 94%, Due March 2025, passed.
- South Bay 2Nearby in Dubai South Residential District. 94%, Due May 2026, passed.
- South Bay 3 PremiumNearby in Dubai South Residential District. 88%.
- South Bay 4 PremiumNearby in Dubai South Residential District. 86%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.
.jpeg&w=3840&q=75)



.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)