The Collective construction progress
The Collective in Dubai South Residential District is 5.7% built at the Land Department inspection of August 2026. Developer Bold Living Real Estate Development. Completion registered for March 2028.
5.7%
Built, at the Land Department site inspection of 20 August 2026
Running behind its date
- Completion date (Land Department)
- March 2028
- Finish at recent pace
- September 2044
- Construction started
- August 2025
- Registered with the Land Department
- November 2025
- Developer
- Bold Living Real Estate Development
- Community
- Dubai South Residential District
- Units
- 94
- Escrow bank
- Emirates Islamic Bank
- Name in Arabic
- ذاكوليكتف
- Land Department project number
- 3888
- Land Department site inspections
- 2
Schedule
Between July 2025 and August 2026 the site added about 0.4 points a month. At that rate it would finish around September 2044, more than three months after the March 2028 date registered with the Land Department.
Site inspections
20 August 2026
5.7%+5.7 pts
17 July 2025
0%
Context
Dubai South Residential District has 40 projects under construction, 40% built on average.
Own a unit in The Collective?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will The Collective be completed?
- The completion date registered with the Dubai Land Department is March 2028. At the pace of its recent inspections the site would reach 100% around September 2044. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of The Collective is built?
- 5.7%, measured at the Land Department site inspection on 20 August 2026. The Land Department engineers have inspected the site 2 times since July 2025.
- Is The Collective delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2028.
- Who is building The Collective?
- The registered developer is Bold Living Real Estate Development.
- Which bank holds the escrow account for The Collective?
- Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- South LivingNearby in Dubai South Residential District. 89%.
- South Bay 1Nearby in Dubai South Residential District. 94%.
- South Bay 2Nearby in Dubai South Residential District. 94%.
- South Bay 3 PremiumNearby in Dubai South Residential District. 88%.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)