The Collective construction progress

The registered completion date for The Collective in Dubai South Residential District is March 2028. At the last site inspection, in November 2026, it was 11% built. The developer is Bold Living Real Estate Development.

11%

Built, at the site inspection of 24 November 2026

Running behind its date

Registered completion date
March 2028
Finish at recent pace
January 2031
Construction started
August 2025
First registered
November 2025
Developer
Bold Living Real Estate Development
Units
94
Escrow bank
Emirates Islamic Bank
Name in Arabic
ذاكوليكتف
Project number
3888
Site inspections
3

Schedule

Between August 2026 and November 2026 the site added about 1.8 points a month. At that rate it would finish around January 2031, more than three months after its registered date of March 2028.

0%25%50%75%100%202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

24 November 2026

11%+5.6 pts

  • The Collective construction site, inspection photo 1, 24 November 2026
  • The Collective construction site, inspection photo 2, 24 November 2026
  • The Collective construction site, inspection photo 3, 24 November 2026
  • The Collective construction site, inspection photo 4, 24 November 2026

20 August 2026

5.7%+5.7 pts

  • The Collective construction site, inspection photo 1, 20 August 2026
  • The Collective construction site, inspection photo 2, 20 August 2026
  • The Collective construction site, inspection photo 3, 20 August 2026
  • The Collective construction site, inspection photo 4, 20 August 2026

17 July 2025

0%

  • The Collective construction site, inspection photo 1, 17 July 2025
  • The Collective construction site, inspection photo 2, 17 July 2025

All 11 site photos, by inspection date

Context

Dubai South Residential District has 37 projects under construction, 43% built on average.

Own a unit in The Collective?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the The Collective handover date?
The registered completion date is March 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around January 2031. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on The Collective?
The Collective was 11% built at the site inspection on 24 November 2026. The site has been inspected 3 times since July 2025. The Land Department took 11 site photos at its inspections.
Is The Collective delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2028.
Who is building The Collective?
The registered developer is Bold Living Real Estate Development.
Which bank holds the escrow account for The Collective?
Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.