Tenora construction progress

The register lists Tenora in Dubai South Residential District as complete, with a registered completion date of January 2016. Its last site inspection on record was in March 2016. The developer is Damac Development.

100%

Built, at the site inspection of 8 March 2016

Construction complete

Registered completion date
January 2016
Construction started
April 2010
First registered
November 2008
Developer
Damac Development
Units
261
Escrow bank
Emirates NBD
Name in Arabic
تينورا
Project number
299
Site inspections
5

Schedule

The register lists Tenora as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%201120132015
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

8 March 2016

98%+30 pts

  • Tenora construction site, inspection photo 1, 8 March 2016
  • Tenora construction site, inspection photo 2, 8 March 2016
  • Tenora construction site, inspection photo 3, 8 March 2016
  • Tenora construction site, inspection photo 4, 8 March 2016

9 August 2015

68%+16 pts

  • Tenora construction site, inspection photo 1, 9 August 2015
  • Tenora construction site, inspection photo 2, 9 August 2015
  • Tenora construction site, inspection photo 3, 9 August 2015
  • Tenora construction site, inspection photo 4, 9 August 2015

13 April 2015

52%+8.0 pts

  • Tenora construction site, inspection photo 1, 13 April 2015
  • Tenora construction site, inspection photo 2, 13 April 2015
  • Tenora construction site, inspection photo 3, 13 April 2015
  • Tenora construction site, inspection photo 4, 13 April 2015

14 December 2014

44%+4.6 pts

  • Tenora construction site, inspection photo 1, 14 December 2014
  • Tenora construction site, inspection photo 2, 14 December 2014
  • Tenora construction site, inspection photo 3, 14 December 2014
  • Tenora construction site, inspection photo 4, 14 December 2014

3 July 2013

40%

  • Tenora construction site, inspection photo 1, 3 July 2013
  • Tenora construction site, inspection photo 2, 3 July 2013
  • Tenora construction site, inspection photo 3, 3 July 2013
  • Tenora construction site, inspection photo 4, 3 July 2013

All 48 site photos, by inspection date

Context

Dubai South Residential District has 37 projects under construction, 43% built on average.

Own a unit in Tenora?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Tenora handover date?
Construction of Tenora is recorded as complete, with a registered completion date of January 2016. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Tenora?
Tenora was 100% built at the site inspection on 8 March 2016. The site has been inspected 5 times since July 2013. The Land Department took 48 site photos at its inspections.
Is Tenora delayed?
The register lists construction as complete.
Who is building Tenora?
The registered developer is Damac Development.
Which bank holds the escrow account for Tenora?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.