Sikanta Residences construction progress
The registered completion date for Sikanta Residences in Dubai South Residential District is March 2027. At the last site inspection, in November 2026, it was 27% built. The developer is Sikanta Real Estate Development.
27%
Built, at the site inspection of 5 November 2026
Running behind its date
- Registered completion date
- March 2027
- Finish at recent pace
- November 2028
- Construction started
- November 2025
- First registered
- September 2025
- Developer
- Sikanta Real Estate Development
- Community
- Dubai South Residential District
- Units
- 64
- Escrow bank
- Emirates Islamic Bank
- Name in Arabic
- سيكانتا ريزيدنسز
- Project number
- 3658
- Site inspections
- 4
Schedule
Between March 2026 and November 2026 the site added about 2.9 points a month. At that rate it would finish around November 2028, more than three months after its registered date of March 2027.
Site inspections
5 November 2026
27%+13 pts
16 July 2026
14%+8.4 pts
27 March 2026
5.4%+5.4 pts
19 May 2025
0%
Context
Dubai South Residential District has 37 projects under construction, 43% built on average.
Own a unit in Sikanta Residences?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Sikanta Residences handover date?
- The registered completion date is March 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around November 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Sikanta Residences?
- Sikanta Residences was 27% built at the site inspection on 5 November 2026. The site has been inspected 4 times since May 2025. The Land Department took 21 site photos at its inspections.
- Is Sikanta Residences delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2027.
- Who is building Sikanta Residences?
- The registered developer is Sikanta Real Estate Development.
- Which bank holds the escrow account for Sikanta Residences?
- Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- South Bay 1Nearby in Dubai South Residential District. 94%, Due March 2025, passed.
- South Bay 2Nearby in Dubai South Residential District. 94%, Due May 2026, passed.
- South Bay 3 PremiumNearby in Dubai South Residential District. 88%.
- South Bay 4 PremiumNearby in Dubai South Residential District. 86%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.