Sikanta Residences construction progress

The registered completion date for Sikanta Residences in Dubai South Residential District is March 2027. At the last site inspection, in November 2026, it was 27% built. The developer is Sikanta Real Estate Development.

27%

Built, at the site inspection of 5 November 2026

Running behind its date

Registered completion date
March 2027
Finish at recent pace
November 2028
Construction started
November 2025
First registered
September 2025
Developer
Sikanta Real Estate Development
Units
64
Escrow bank
Emirates Islamic Bank
Name in Arabic
سيكانتا ريزيدنسز
Project number
3658
Site inspections
4

Schedule

Between March 2026 and November 2026 the site added about 2.9 points a month. At that rate it would finish around November 2028, more than three months after its registered date of March 2027.

0%25%50%75%100%20262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

5 November 2026

27%+13 pts

  • Sikanta Residences construction site, inspection photo 1, 5 November 2026
  • Sikanta Residences construction site, inspection photo 2, 5 November 2026
  • Sikanta Residences construction site, inspection photo 3, 5 November 2026
  • Sikanta Residences construction site, inspection photo 4, 5 November 2026

16 July 2026

14%+8.4 pts

  • Sikanta Residences construction site, inspection photo 1, 16 July 2026
  • Sikanta Residences construction site, inspection photo 2, 16 July 2026
  • Sikanta Residences construction site, inspection photo 3, 16 July 2026
  • Sikanta Residences construction site, inspection photo 4, 16 July 2026

27 March 2026

5.4%+5.4 pts

  • Sikanta Residences construction site, inspection photo 1, 27 March 2026
  • Sikanta Residences construction site, inspection photo 2, 27 March 2026
  • Sikanta Residences construction site, inspection photo 3, 27 March 2026
  • Sikanta Residences construction site, inspection photo 4, 27 March 2026

19 May 2025

0%

  • Sikanta Residences construction site, inspection photo 1, 19 May 2025
  • Sikanta Residences construction site, inspection photo 2, 19 May 2025

All 21 site photos, by inspection date

Context

Dubai South Residential District has 37 projects under construction, 43% built on average.

Own a unit in Sikanta Residences?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Sikanta Residences handover date?
The registered completion date is March 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around November 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Sikanta Residences?
Sikanta Residences was 27% built at the site inspection on 5 November 2026. The site has been inspected 4 times since May 2025. The Land Department took 21 site photos at its inspections.
Is Sikanta Residences delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2027.
Who is building Sikanta Residences?
The registered developer is Sikanta Real Estate Development.
Which bank holds the escrow account for Sikanta Residences?
Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.