Lincoln Star Residence II construction progress

The registered completion date for Lincoln Star Residence II in Dubai South Residential District is August 2027. At the last site inspection, in April 2026, it was 5.3% built. The developer is Lincoln Rise Real Estate Development.

5.3%

Built, at the site inspection of 9 April 2026

Running behind its date

Registered completion date
August 2027
Finish at recent pace
August 2037
Construction started
September 2025
First registered
May 2026
Developer
Lincoln Rise Real Estate Development
Units
56
Escrow bank
Ajman Bank
Name in Arabic
Iiلينكولن ستار ريزيدنس
Project number
4027
Site inspections
2

Schedule

Between August 2025 and April 2026 the site added about 0.7 points a month. At that rate it would finish around August 2037, more than three months after its registered date of August 2027.

0%25%50%75%100%20262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

9 April 2026

5.3%+5.3 pts

  • Lincoln Star Residence II construction site, inspection photo 1, 9 April 2026
  • Lincoln Star Residence II construction site, inspection photo 2, 9 April 2026
  • Lincoln Star Residence II construction site, inspection photo 3, 9 April 2026
  • Lincoln Star Residence II construction site, inspection photo 4, 9 April 2026

21 August 2025

0%

  • Lincoln Star Residence II construction site, inspection photo 1, 21 August 2025
  • Lincoln Star Residence II construction site, inspection photo 2, 21 August 2025

All 6 site photos, by inspection date

Context

Dubai South Residential District has 37 projects under construction, 43% built on average.

Own a unit in Lincoln Star Residence II?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Lincoln Star Residence II handover date?
The registered completion date is August 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around August 2037. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Lincoln Star Residence II?
Lincoln Star Residence II was 5.3% built at the site inspection on 9 April 2026. The site has been inspected 2 times since August 2025. The Land Department took 6 site photos at its inspections.
Is Lincoln Star Residence II delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of August 2027.
Who is building Lincoln Star Residence II?
The registered developer is Lincoln Rise Real Estate Development.
Which bank holds the escrow account for Lincoln Star Residence II?
Ajman Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.