Greenfield Living construction progress

Greenfield Living in Dubai South Residential District is 33% built at the Land Department inspection of April 2026. Developer Greenfield Real Estate Development. Completion registered for December 2026.

33%

Built, at the Land Department site inspection of 17 April 2026

Running behind its date

Completion date (Land Department)
December 2026
Finish at recent pace
December 2027
Construction started
April 2025
Registered with the Land Department
September 2025
Developer
Greenfield Real Estate Development
Units
52
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
جرينفيلد ليفينج
Land Department project number
3821
Land Department site inspections
3

Schedule

Between June 2025 and April 2026 the site added about 3.4 points a month. At that rate it would finish around December 2027, more than three months after the December 2026 date registered with the Land Department.

0%25%50%75%100%2026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

17 April 2026

33%+18 pts

  • Greenfield Living construction site, Land Department inspection photo 1, 17 April 2026
  • Greenfield Living construction site, Land Department inspection photo 2, 17 April 2026
  • Greenfield Living construction site, Land Department inspection photo 3, 17 April 2026
  • Greenfield Living construction site, Land Department inspection photo 4, 17 April 2026

5 December 2025

16%+16 pts

  • Greenfield Living construction site, Land Department inspection photo 1, 5 December 2025
  • Greenfield Living construction site, Land Department inspection photo 2, 5 December 2025
  • Greenfield Living construction site, Land Department inspection photo 3, 5 December 2025
  • Greenfield Living construction site, Land Department inspection photo 4, 5 December 2025

23 June 2025

0%

  • Greenfield Living construction site, Land Department inspection photo 1, 23 June 2025
  • Greenfield Living construction site, Land Department inspection photo 2, 23 June 2025

All 12 site photos, by inspection date

Context

Dubai South Residential District has 40 projects under construction, 40% built on average.

Own a unit in Greenfield Living?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Greenfield Living be completed?
The completion date registered with the Dubai Land Department is December 2026. At the pace of its recent inspections the site would reach 100% around December 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Greenfield Living is built?
33%, measured at the Land Department site inspection on 17 April 2026. The Land Department engineers have inspected the site 3 times since June 2025.
Is Greenfield Living delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2026.
Who is building Greenfield Living?
The registered developer is Greenfield Real Estate Development.
Which bank holds the escrow account for Greenfield Living?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.