Greenfield Living construction progress
The registered completion date for Greenfield Living in Dubai South Residential District is December 2026. At the last site inspection, in April 2026, it was 33% built. The developer is Greenfield Real Estate Development.
33%
Built, at the site inspection of 17 April 2026
Running behind its date
- Registered completion date
- December 2026
- Finish at recent pace
- December 2027
- Construction started
- April 2025
- First registered
- September 2025
- Developer
- Greenfield Real Estate Development
- Community
- Dubai South Residential District
- Units
- 52
- Escrow bank
- Abu Dhabi Commercial Bank
- Name in Arabic
- جرينفيلد ليفينج
- Project number
- 3821
- Site inspections
- 3
Schedule
Between June 2025 and April 2026 the site added about 3.4 points a month. At that rate it would finish around December 2027, more than three months after its registered date of December 2026.
Site inspections
17 April 2026
33%+18 pts
5 December 2025
16%+16 pts
23 June 2025
0%
Context
Dubai South Residential District has 37 projects under construction, 43% built on average.
Own a unit in Greenfield Living?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Greenfield Living handover date?
- The registered completion date is December 2026. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around December 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Greenfield Living?
- Greenfield Living was 33% built at the site inspection on 17 April 2026. The site has been inspected 3 times since June 2025. The Land Department took 12 site photos at its inspections.
- Is Greenfield Living delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2026.
- Who is building Greenfield Living?
- The registered developer is Greenfield Real Estate Development.
- Which bank holds the escrow account for Greenfield Living?
- Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- South Bay 1Nearby in Dubai South Residential District. 94%, Due March 2025, passed.
- South Bay 2Nearby in Dubai South Residential District. 94%, Due May 2026, passed.
- South Bay 3 PremiumNearby in Dubai South Residential District. 88%.
- South Bay 4 PremiumNearby in Dubai South Residential District. 86%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.



.jpeg&w=3840&q=75)