Golden Woods Albab Views construction progress
The registered completion date for Golden Woods Albab Views in Dubai South Residential District is February 2027. At the last site inspection, in June 2026, it was 30% built. The developer is A G W Real Estate Development.
30%
Built, at the site inspection of 11 June 2026
Running behind its date
- Registered completion date
- February 2027
- Finish at recent pace
- May 2029
- Construction started
- March 2025
- First registered
- May 2025
- Developer
- A G W Real Estate Development
- Community
- Dubai South Residential District
- Units
- 132
- Escrow bank
- Abu Dhabi Islamic Bank
- Name in Arabic
- جولدن وودز الباب فيوز
- Project number
- 3591
- Site inspections
- 2
Schedule
Between March 2025 and June 2026 the site added about 2.0 points a month. At that rate it would finish around May 2029, more than three months after its registered date of February 2027.
Site inspections
11 June 2026
30%+30 pts
6 March 2025
0%
Context
Dubai South Residential District has 37 projects under construction, 43% built on average.
Own a unit in Golden Woods Albab Views?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Golden Woods Albab Views handover date?
- The registered completion date is February 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around May 2029. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Golden Woods Albab Views?
- Golden Woods Albab Views was 30% built at the site inspection on 11 June 2026. The site has been inspected 2 times since March 2025. The Land Department took 8 site photos at its inspections.
- Is Golden Woods Albab Views delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of February 2027.
- Who is building Golden Woods Albab Views?
- The registered developer is A G W Real Estate Development.
- Which bank holds the escrow account for Golden Woods Albab Views?
- Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- South Bay 1Nearby in Dubai South Residential District. 94%, Due March 2025, passed.
- South Bay 2Nearby in Dubai South Residential District. 94%, Due May 2026, passed.
- South Bay 3 PremiumNearby in Dubai South Residential District. 88%.
- South Bay 4 PremiumNearby in Dubai South Residential District. 86%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.

