Cresswell Views construction progress

The registered completion date for Cresswell Views in Dubai South Residential District is December 2026. At the last site inspection, in November 2026, it was 70% built. The developer is Adev Properties (Br Of Arady Properties - )(Dubai Branch ).

70%

Built, at the site inspection of 20 November 2026

Running behind its date

Registered completion date
December 2026
Finish at recent pace
August 2027
Construction started
December 2024
First registered
June 2025
Developer
Adev Properties (Br Of Arady Properties - )(Dubai Branch )
Units
56
Escrow bank
Mashreq Bank
Name in Arabic
كريسسويل فيوس
Project number
3583
Site inspections
4

Schedule

Between January 2026 and November 2026 the site added about 3.3 points a month. At that rate it would finish around August 2027, more than three months after its registered date of December 2026.

0%25%50%75%100%20252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

20 November 2026

70%+9.8 pts

  • Cresswell Views construction site, inspection photo 1, 20 November 2026
  • Cresswell Views construction site, inspection photo 2, 20 November 2026
  • Cresswell Views construction site, inspection photo 3, 20 November 2026
  • Cresswell Views construction site, inspection photo 4, 20 November 2026

22 July 2026

60%+24 pts

  • Cresswell Views construction site, inspection photo 1, 22 July 2026
  • Cresswell Views construction site, inspection photo 2, 22 July 2026
  • Cresswell Views construction site, inspection photo 3, 22 July 2026
  • Cresswell Views construction site, inspection photo 4, 22 July 2026

13 January 2026

37%+37 pts

  • Cresswell Views construction site, inspection photo 1, 13 January 2026
  • Cresswell Views construction site, inspection photo 2, 13 January 2026
  • Cresswell Views construction site, inspection photo 3, 13 January 2026
  • Cresswell Views construction site, inspection photo 4, 13 January 2026

20 March 2025

0%

  • Cresswell Views construction site, inspection photo 1, 20 March 2025
  • Cresswell Views construction site, inspection photo 2, 20 March 2025

All 32 site photos, by inspection date

Context

Dubai South Residential District has 37 projects under construction, 43% built on average.

Own a unit in Cresswell Views?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Cresswell Views handover date?
The registered completion date is December 2026. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around August 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Cresswell Views?
Cresswell Views was 70% built at the site inspection on 20 November 2026. The site has been inspected 4 times since March 2025. The Land Department took 32 site photos at its inspections.
Is Cresswell Views delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2026.
Who is building Cresswell Views?
The registered developer is Adev Properties (Br Of Arady Properties - )(Dubai Branch ).
Which bank holds the escrow account for Cresswell Views?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.