Cresswell Views construction progress

Cresswell Views in Dubai South Residential District is 60% built at the Land Department inspection of July 2026. Developer Adev Properties (Br Of Arady Properties - )(Dubai Branch ). Completion registered for December 2026.

60%

Built, at the Land Department site inspection of 22 July 2026

Running behind its date

Completion date (Land Department)
December 2026
Finish at recent pace
June 2027
Construction started
December 2024
Registered with the Land Department
June 2025
Developer
Adev Properties (Br Of Arady Properties - )(Dubai Branch )
Units
56
Escrow bank
Mashreq Bank
Name in Arabic
كريسسويل فيوس
Land Department project number
3583
Land Department site inspections
3

Schedule

Between January 2026 and July 2026 the site added about 3.8 points a month. At that rate it would finish around June 2027, more than three months after the December 2026 date registered with the Land Department.

0%25%50%75%100%20252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

22 July 2026

60%+24 pts

  • Cresswell Views construction site, Land Department inspection photo 1, 22 July 2026
  • Cresswell Views construction site, Land Department inspection photo 2, 22 July 2026
  • Cresswell Views construction site, Land Department inspection photo 3, 22 July 2026
  • Cresswell Views construction site, Land Department inspection photo 4, 22 July 2026

13 January 2026

37%+37 pts

  • Cresswell Views construction site, Land Department inspection photo 1, 13 January 2026
  • Cresswell Views construction site, Land Department inspection photo 2, 13 January 2026
  • Cresswell Views construction site, Land Department inspection photo 3, 13 January 2026
  • Cresswell Views construction site, Land Department inspection photo 4, 13 January 2026

20 March 2025

0%

  • Cresswell Views construction site, Land Department inspection photo 1, 20 March 2025
  • Cresswell Views construction site, Land Department inspection photo 2, 20 March 2025

All 20 site photos, by inspection date

Context

Dubai South Residential District has 40 projects under construction, 40% built on average. Cresswell Views is ahead of that average.

Own a unit in Cresswell Views?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Track the handover

Questions

When will Cresswell Views be completed?
The completion date registered with the Dubai Land Department is December 2026. At the pace of its recent inspections the site would reach 100% around June 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Cresswell Views is built?
60%, measured at the Land Department site inspection on 22 July 2026. The Land Department engineers have inspected the site 3 times since March 2025.
Is Cresswell Views delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2026.
Who is building Cresswell Views?
The registered developer is Adev Properties (Br Of Arady Properties - )(Dubai Branch ).
Which bank holds the escrow account for Cresswell Views?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.