Cresswell Homes construction progress

The registered completion date for Cresswell Homes in Dubai South Residential District is December 2026. At the last site inspection, in November 2026, it was 61% built. The developer is Abdulwahed Faqeeh Properties.

61%

Built, at the site inspection of 5 November 2026

Running behind its date

Registered completion date
December 2026
Finish at recent pace
August 2027
Construction started
April 2025
First registered
June 2026
Developer
Abdulwahed Faqeeh Properties
Units
70
Escrow bank
Emirates NBD
Name in Arabic
كريسويل هومس
Project number
3299
Site inspections
3

Schedule

Between March 2026 and November 2026 the site added about 4.3 points a month. At that rate it would finish around August 2027, more than three months after its registered date of December 2026.

0%25%50%75%100%20252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

5 November 2026

61%+33 pts

  • Cresswell Homes construction site, inspection photo 1, 5 November 2026
  • Cresswell Homes construction site, inspection photo 2, 5 November 2026
  • Cresswell Homes construction site, inspection photo 3, 5 November 2026
  • Cresswell Homes construction site, inspection photo 4, 5 November 2026

19 March 2026

29%+29 pts

  • Cresswell Homes construction site, inspection photo 1, 19 March 2026
  • Cresswell Homes construction site, inspection photo 2, 19 March 2026
  • Cresswell Homes construction site, inspection photo 3, 19 March 2026

18 September 2024

0%

  • Cresswell Homes construction site, inspection photo 1, 18 September 2024
  • Cresswell Homes construction site, inspection photo 2, 18 September 2024
  • Cresswell Homes construction site, inspection photo 3, 18 September 2024

All 15 site photos, by inspection date

Context

Dubai South Residential District has 37 projects under construction, 43% built on average.

Own a unit in Cresswell Homes?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Cresswell Homes handover date?
The registered completion date is December 2026. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around August 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Cresswell Homes?
Cresswell Homes was 61% built at the site inspection on 5 November 2026. The site has been inspected 3 times since September 2024. The Land Department took 15 site photos at its inspections.
Is Cresswell Homes delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2026.
Who is building Cresswell Homes?
The registered developer is Abdulwahed Faqeeh Properties.
Which bank holds the escrow account for Cresswell Homes?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.