Bling Avenue 1 construction progress
Bling Avenue 1 in Dubai South Residential District was registered to complete in July 2026 and is still under construction. At the last site inspection, in June 2026, it was 68% built. The developer is Bling Development Dwc.
68%
Built, at the site inspection of 16 June 2026
4 months past its registered completion date
- Registered completion date
- July 2026
- Finish at recent pace
- May 2027
- Construction started
- October 2024
- First registered
- April 2025
- Developer
- Bling Development Dwc
- Community
- Dubai South Residential District
- Units
- 40
- Escrow bank
- United Bank Limited
- Name in Arabic
- بلينج افينو 1
- Project number
- 3582
- Site inspections
- 4
Schedule
Bling Avenue 1 was registered to complete in July 2026, 4 months ago, and is still under construction. Over the last year of inspections it has added about 2.9 points a month. Kept at that rate, the site would reach 100% around May 2027.
Site inspections
16 June 2026
68%+21 pts
26 November 2025
47%+11 pts
17 July 2025
37%+19 pts
27 February 2025
18%
Context
Dubai South Residential District has 37 projects under construction, 43% built on average.
Own a unit in Bling Avenue 1?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Bling Avenue 1 handover date?
- The registered completion date was July 2026, and the register still lists Bling Avenue 1 as under construction. At the pace of its recent inspections the site would reach 100% around May 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Bling Avenue 1?
- Bling Avenue 1 was 68% built at the site inspection on 16 June 2026. The site has been inspected 4 times since February 2025. The Land Department took 29 site photos at its inspections.
- Is Bling Avenue 1 delayed?
- Yes. Its registered completion date of July 2026 has passed and the project is still listed as under construction.
- Who is building Bling Avenue 1?
- The registered developer is Bling Development Dwc.
- Which bank holds the escrow account for Bling Avenue 1?
- United Bank Limited. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- South Bay 1Nearby in Dubai South Residential District. 94%, Due March 2025, passed.
- South Bay 2Nearby in Dubai South Residential District. 94%, Due May 2026, passed.
- South Bay 3 PremiumNearby in Dubai South Residential District. 88%.
- South Bay 4 PremiumNearby in Dubai South Residential District. 86%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.