Avion Residence construction progress

The registered completion date for Avion Residence in Dubai South Residential District is March 2027. At the last site inspection, in October 2026, it was 36% built. The developer is Sky View Development.

36%

Built, at the site inspection of 1 October 2026

Running behind its date

Registered completion date
March 2027
Finish at recent pace
May 2029
Construction started
February 2025
First registered
May 2025
Developer
Sky View Development
Units
66
Escrow bank
Emirates NBD
Name in Arabic
أفيون ريزيدنس
Project number
3653
Site inspections
4

Schedule

Between November 2025 and October 2026 the site added about 2.1 points a month. At that rate it would finish around May 2029, more than three months after its registered date of March 2027.

0%25%50%75%100%20262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

1 October 2026

36%+15 pts

  • Avion Residence construction site, inspection photo 1, 1 October 2026
  • Avion Residence construction site, inspection photo 2, 1 October 2026
  • Avion Residence construction site, inspection photo 3, 1 October 2026
  • Avion Residence construction site, inspection photo 4, 1 October 2026

3 April 2026

20%+7.0 pts

  • Avion Residence construction site, inspection photo 1, 3 April 2026
  • Avion Residence construction site, inspection photo 2, 3 April 2026
  • Avion Residence construction site, inspection photo 3, 3 April 2026
  • Avion Residence construction site, inspection photo 4, 3 April 2026

7 November 2025

13%+13 pts

  • Avion Residence construction site, inspection photo 1, 7 November 2025
  • Avion Residence construction site, inspection photo 2, 7 November 2025
  • Avion Residence construction site, inspection photo 3, 7 November 2025
  • Avion Residence construction site, inspection photo 4, 7 November 2025

7 April 2025

0%

  • Avion Residence construction site, inspection photo 1, 7 April 2025

All 18 site photos, by inspection date

Context

Dubai South Residential District has 37 projects under construction, 43% built on average.

Own a unit in Avion Residence?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Avion Residence handover date?
The registered completion date is March 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around May 2029. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Avion Residence?
Avion Residence was 36% built at the site inspection on 1 October 2026. The site has been inspected 4 times since April 2025. The Land Department took 18 site photos at its inspections.
Is Avion Residence delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2027.
Who is building Avion Residence?
The registered developer is Sky View Development.
Which bank holds the escrow account for Avion Residence?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.