Aero 1 construction progress

Aero 1 in Dubai South Residential District is 36% built at the Land Department inspection of September 2026. Developer Bithaus Real Estate Development. Completion registered for July 2027.

36%

Built, at the Land Department site inspection of 29 September 2026

Running behind its date

Completion date (Land Department)
July 2027
Finish at recent pace
February 2028
Construction started
July 2025
Registered with the Land Department
July 2025
Developer
Bithaus Real Estate Development
Units
48
Escrow bank
First Abu Dhabi Bank
Name in Arabic
ايرو 1
Land Department project number
3728
Land Department site inspections
4

Schedule

Between January 2026 and September 2026 the site added about 3.9 points a month. At that rate it would finish around February 2028, more than three months after the July 2027 date registered with the Land Department.

0%25%50%75%100%20262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

29 September 2026

36%+24 pts

  • Aero 1 construction site, Land Department inspection photo 1, 29 September 2026
  • Aero 1 construction site, Land Department inspection photo 2, 29 September 2026
  • Aero 1 construction site, Land Department inspection photo 3, 29 September 2026
  • Aero 1 construction site, Land Department inspection photo 4, 29 September 2026

7 May 2026

12%+8.7 pts

  • Aero 1 construction site, Land Department inspection photo 1, 7 May 2026
  • Aero 1 construction site, Land Department inspection photo 2, 7 May 2026
  • Aero 1 construction site, Land Department inspection photo 3, 7 May 2026
  • Aero 1 construction site, Land Department inspection photo 4, 7 May 2026

15 January 2026

2.8%+2.8 pts

  • Aero 1 construction site, Land Department inspection photo 1, 15 January 2026
  • Aero 1 construction site, Land Department inspection photo 2, 15 January 2026
  • Aero 1 construction site, Land Department inspection photo 3, 15 January 2026
  • Aero 1 construction site, Land Department inspection photo 4, 15 January 2026

8 May 2025

0%

  • Aero 1 construction site, Land Department inspection photo 1, 8 May 2025
  • Aero 1 construction site, Land Department inspection photo 2, 8 May 2025

All 18 site photos, by inspection date

Context

Dubai South Residential District has 40 projects under construction, 40% built on average. Aero 1 is behind that average.

Own a unit in Aero 1?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Track the handover

Questions

When will Aero 1 be completed?
The completion date registered with the Dubai Land Department is July 2027. At the pace of its recent inspections the site would reach 100% around February 2028. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Aero 1 is built?
36%, measured at the Land Department site inspection on 29 September 2026. The Land Department engineers have inspected the site 4 times since May 2025.
Is Aero 1 delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of July 2027.
Who is building Aero 1?
The registered developer is Bithaus Real Estate Development.
Which bank holds the escrow account for Aero 1?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.