Aero 1 construction progress

The registered completion date for Aero 1 in Dubai South Residential District is July 2027. At the last site inspection, in September 2026, it was 36% built. The developer is Bithaus Real Estate Development.

36%

Built, at the site inspection of 29 September 2026

Running behind its date

Registered completion date
July 2027
Finish at recent pace
February 2028
Construction started
July 2025
First registered
July 2025
Developer
Bithaus Real Estate Development
Units
48
Escrow bank
First Abu Dhabi Bank
Name in Arabic
ايرو 1
Project number
3728
Site inspections
4

Schedule

Between January 2026 and September 2026 the site added about 3.9 points a month. At that rate it would finish around February 2028, more than three months after its registered date of July 2027.

0%25%50%75%100%20262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

29 September 2026

36%+24 pts

  • Aero 1 construction site, inspection photo 1, 29 September 2026
  • Aero 1 construction site, inspection photo 2, 29 September 2026
  • Aero 1 construction site, inspection photo 3, 29 September 2026
  • Aero 1 construction site, inspection photo 4, 29 September 2026

7 May 2026

12%+8.7 pts

  • Aero 1 construction site, inspection photo 1, 7 May 2026
  • Aero 1 construction site, inspection photo 2, 7 May 2026
  • Aero 1 construction site, inspection photo 3, 7 May 2026
  • Aero 1 construction site, inspection photo 4, 7 May 2026

15 January 2026

2.8%+2.8 pts

  • Aero 1 construction site, inspection photo 1, 15 January 2026
  • Aero 1 construction site, inspection photo 2, 15 January 2026
  • Aero 1 construction site, inspection photo 3, 15 January 2026
  • Aero 1 construction site, inspection photo 4, 15 January 2026

8 May 2025

0%

  • Aero 1 construction site, inspection photo 1, 8 May 2025
  • Aero 1 construction site, inspection photo 2, 8 May 2025

All 18 site photos, by inspection date

Context

Dubai South Residential District has 37 projects under construction, 43% built on average.

Own a unit in Aero 1?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Aero 1 handover date?
The registered completion date is July 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around February 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Aero 1?
Aero 1 was 36% built at the site inspection on 29 September 2026. The site has been inspected 4 times since May 2025. The Land Department took 18 site photos at its inspections.
Is Aero 1 delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of July 2027.
Who is building Aero 1?
The registered developer is Bithaus Real Estate Development.
Which bank holds the escrow account for Aero 1?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.