Coventry Gardens construction progress

Coventry Gardens in Dubai Land Residence Complex is 1.2% built at the Land Department inspection of September 2025. Developer G F S Real Estate. Completion registered for March 2027.

1.2%

Built, at the Land Department site inspection of 25 September 2025

Running behind its date

Completion date (Land Department)
March 2027
Finish at recent pace
April 2098
Construction started
December 2024
Registered with the Land Department
January 2025
Units
97
Escrow bank
Mashreq Bank
Name in Arabic
حدائق كوفنتري
Land Department project number
3342
Land Department site inspections
2

Schedule

Between October 2024 and September 2025 the site added about 0.1 points a month. At that rate it would finish around April 2098, more than three months after the March 2027 date registered with the Land Department.

0%25%50%75%100%202520262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

25 September 2025

1.2%+1.2 pts

  • Coventry Gardens construction site, Land Department inspection photo 1, 25 September 2025
  • Coventry Gardens construction site, Land Department inspection photo 2, 25 September 2025
  • Coventry Gardens construction site, Land Department inspection photo 3, 25 September 2025
  • Coventry Gardens construction site, Land Department inspection photo 4, 25 September 2025

30 October 2024

0%

  • Coventry Gardens construction site, Land Department inspection photo 1, 30 October 2024
  • Coventry Gardens construction site, Land Department inspection photo 2, 30 October 2024

All 7 site photos, by inspection date

Context

Dubai Land Residence Complex has 65 projects under construction, 24% built on average.

G F S Real Estate has 7 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Coventry Gardens?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Coventry Gardens be completed?
The completion date registered with the Dubai Land Department is March 2027. At the pace of its recent inspections the site would reach 100% around April 2098. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Coventry Gardens is built?
1.2%, measured at the Land Department site inspection on 25 September 2025. The Land Department engineers have inspected the site 2 times since October 2024.
Is Coventry Gardens delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2027.
Who is building Coventry Gardens?
The registered developer is G F S Real Estate. It has 6 other projects under construction in Dubai.
Which bank holds the escrow account for Coventry Gardens?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.