Keturah Resort construction photos

85 photos taken by Dubai Land Department engineers at 13 site inspections, newest first. The percentage is how much of Keturah Resort was built on the day of each visit.

30 July 202615% built

24 April 202614% built

11 February 202510% built

6 June 20248.8% built

20 March 20247.7% built

2 October 20235.0% built

5 May 20234.8% built

16 September 20224.7% built

11 May 20224.7% built

26 October 20213.7% built

18 June 20203.7% built

23 September 20193.7% built

26 July 20182.2% built

Back to Keturah Resort construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.