Damac Lagoons - Venice (1) construction photos

62 photos from 11 site inspections, newest first. The percentage is how much of Damac Lagoons - Venice (1) was built on the day of each visit.

17 July 202674% built

22 April 202668% built

13 November 202562% built

24 June 202555% built

6 February 202550% built

19 September 202437% built

20 May 202423% built

7 December 20236.2% built

22 August 20231.6% built

4 May 20230.4% built

21 December 20220.1% built

Back to Damac Lagoons - Venice (1) construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.