Damac Lagoons - Santorini (3) construction progress

The register lists Damac Lagoons - Santorini (3) in Damac Lagoons as complete, with a registered completion date of July 2025. Its last site inspection on record was in April 2026. The developer is Island Oasis Properties.

100%

Built, at the site inspection of 9 April 2026

Construction complete

Registered completion date
July 2025
Construction started
January 2022
First registered
October 2021
Community
Damac Lagoons
Units
96
Escrow bank
Emirates NBD
Name in Arabic
داماك لاجونز - سانتوريني 3
Project number
2320
Site inspections
11

Schedule

The register lists Damac Lagoons - Santorini (3) as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2023202420252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

9 April 2026

100%+4.8 pts

  • Damac Lagoons - Santorini (3) construction site, inspection photo 1, 9 April 2026
  • Damac Lagoons - Santorini (3) construction site, inspection photo 2, 9 April 2026
  • Damac Lagoons - Santorini (3) construction site, inspection photo 3, 9 April 2026
  • Damac Lagoons - Santorini (3) construction site, inspection photo 4, 9 April 2026

21 November 2025

95%+4.4 pts

  • Damac Lagoons - Santorini (3) construction site, inspection photo 1, 21 November 2025
  • Damac Lagoons - Santorini (3) construction site, inspection photo 2, 21 November 2025
  • Damac Lagoons - Santorini (3) construction site, inspection photo 3, 21 November 2025
  • Damac Lagoons - Santorini (3) construction site, inspection photo 4, 21 November 2025

18 June 2025

91%+11 pts

  • Damac Lagoons - Santorini (3) construction site, inspection photo 1, 18 June 2025
  • Damac Lagoons - Santorini (3) construction site, inspection photo 2, 18 June 2025
  • Damac Lagoons - Santorini (3) construction site, inspection photo 3, 18 June 2025
  • Damac Lagoons - Santorini (3) construction site, inspection photo 4, 18 June 2025

27 February 2025

80%+10 pts

  • Damac Lagoons - Santorini (3) construction site, inspection photo 1, 27 February 2025
  • Damac Lagoons - Santorini (3) construction site, inspection photo 2, 27 February 2025
  • Damac Lagoons - Santorini (3) construction site, inspection photo 3, 27 February 2025
  • Damac Lagoons - Santorini (3) construction site, inspection photo 4, 27 February 2025

12 September 2024

70%+26 pts

  • Damac Lagoons - Santorini (3) construction site, inspection photo 1, 12 September 2024
  • Damac Lagoons - Santorini (3) construction site, inspection photo 2, 12 September 2024
  • Damac Lagoons - Santorini (3) construction site, inspection photo 3, 12 September 2024
  • Damac Lagoons - Santorini (3) construction site, inspection photo 4, 12 September 2024

17 April 2024

44%+16 pts

  • Damac Lagoons - Santorini (3) construction site, inspection photo 1, 17 April 2024
  • Damac Lagoons - Santorini (3) construction site, inspection photo 2, 17 April 2024
  • Damac Lagoons - Santorini (3) construction site, inspection photo 3, 17 April 2024
  • Damac Lagoons - Santorini (3) construction site, inspection photo 4, 17 April 2024

9 October 2023

28%+16 pts

  • Damac Lagoons - Santorini (3) construction site, inspection photo 1, 9 October 2023
  • Damac Lagoons - Santorini (3) construction site, inspection photo 2, 9 October 2023
  • Damac Lagoons - Santorini (3) construction site, inspection photo 3, 9 October 2023
  • Damac Lagoons - Santorini (3) construction site, inspection photo 4, 9 October 2023

9 June 2023

12%+10 pts

  • Damac Lagoons - Santorini (3) construction site, inspection photo 1, 9 June 2023
  • Damac Lagoons - Santorini (3) construction site, inspection photo 2, 9 June 2023
  • Damac Lagoons - Santorini (3) construction site, inspection photo 3, 9 June 2023
  • Damac Lagoons - Santorini (3) construction site, inspection photo 4, 9 June 2023

3 February 2023

2.1%+1.4 pts

  • Damac Lagoons - Santorini (3) construction site, inspection photo 1, 3 February 2023
  • Damac Lagoons - Santorini (3) construction site, inspection photo 2, 3 February 2023
  • Damac Lagoons - Santorini (3) construction site, inspection photo 3, 3 February 2023
  • Damac Lagoons - Santorini (3) construction site, inspection photo 4, 3 February 2023

22 September 2022

0.7%+0.6 pts

  • Damac Lagoons - Santorini (3) construction site, inspection photo 1, 22 September 2022
  • Damac Lagoons - Santorini (3) construction site, inspection photo 2, 22 September 2022
  • Damac Lagoons - Santorini (3) construction site, inspection photo 3, 22 September 2022

All 74 site photos, by inspection date

Context

Damac Lagoons has 5 projects under construction, 79% built on average.

Island Oasis Properties has 26 projects under construction in Dubai; 7 have passed their registered completion date.

Own a unit in Damac Lagoons - Santorini (3)?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Damac Lagoons - Santorini (3) handover date?
Construction of Damac Lagoons - Santorini (3) is recorded as complete, with a registered completion date of July 2025. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Damac Lagoons - Santorini (3)?
Damac Lagoons - Santorini (3) was 100% built at the site inspection on 9 April 2026. The site has been inspected 11 times since May 2022. The Land Department took 74 site photos at its inspections.
Is Damac Lagoons - Santorini (3) delayed?
The register lists construction as complete.
Who is building Damac Lagoons - Santorini (3)?
The registered developer is Island Oasis Properties. It has 26 other projects under construction in Dubai.
Which bank holds the escrow account for Damac Lagoons - Santorini (3)?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.