Damac Lagoons - Nice 1 construction photos
68 photos taken by Dubai Land Department engineers at 11 site inspections, newest first. The percentage is how much of Damac Lagoons - Nice 1 was built on the day of each visit.
10 August 202694% built
9 June 202693% built
20 November 202578% built
23 June 202568% built
24 February 202558% built
22 September 202451% built
1 May 202434% built
9 October 202316% built
12 June 20237.4% built
3 February 20230.5% built
10 August 20220.1% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.








.jpeg&w=3840&q=75)


.jpeg&w=3840&q=75)



.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)






.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)