Damac Hills - Piccadilly Green construction progress

The register lists Damac Hills - Piccadilly Green in Damac Hills as complete, with a registered completion date of February 2018. Its last site inspection on record was in February 2018. The developer is Damac Crescent Properties.

100%

Built, at the site inspection of 14 February 2018

Construction complete

Registered completion date
February 2018
Construction started
July 2013
First registered
June 2013
Community
Damac Hills
Units
163
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
داماك هيلز - بيكاديلي جرين
Project number
1357
Site inspections
10

Schedule

The register lists Damac Hills - Piccadilly Green as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20142015201620172018
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

14 February 2018

100%+2.0 pts

  • Damac Hills - Piccadilly Green construction site, inspection photo 1, 14 February 2018
  • Damac Hills - Piccadilly Green construction site, inspection photo 2, 14 February 2018
  • Damac Hills - Piccadilly Green construction site, inspection photo 3, 14 February 2018
  • Damac Hills - Piccadilly Green construction site, inspection photo 4, 14 February 2018

6 September 2017

98%+0.8 pts

  • Damac Hills - Piccadilly Green construction site, inspection photo 1, 6 September 2017
  • Damac Hills - Piccadilly Green construction site, inspection photo 2, 6 September 2017
  • Damac Hills - Piccadilly Green construction site, inspection photo 3, 6 September 2017
  • Damac Hills - Piccadilly Green construction site, inspection photo 4, 6 September 2017

23 May 2017

97%+9.9 pts

  • Damac Hills - Piccadilly Green construction site, inspection photo 1, 23 May 2017
  • Damac Hills - Piccadilly Green construction site, inspection photo 2, 23 May 2017
  • Damac Hills - Piccadilly Green construction site, inspection photo 3, 23 May 2017
  • Damac Hills - Piccadilly Green construction site, inspection photo 4, 23 May 2017

17 January 2017

87%+9.2 pts

  • Damac Hills - Piccadilly Green construction site, inspection photo 1, 17 January 2017
  • Damac Hills - Piccadilly Green construction site, inspection photo 2, 17 January 2017
  • Damac Hills - Piccadilly Green construction site, inspection photo 3, 17 January 2017
  • Damac Hills - Piccadilly Green construction site, inspection photo 4, 17 January 2017

7 November 2016

78%+27 pts

  • Damac Hills - Piccadilly Green construction site, inspection photo 1, 7 November 2016
  • Damac Hills - Piccadilly Green construction site, inspection photo 2, 7 November 2016
  • Damac Hills - Piccadilly Green construction site, inspection photo 3, 7 November 2016
  • Damac Hills - Piccadilly Green construction site, inspection photo 4, 7 November 2016

15 May 2016

51%+8.5 pts

  • Damac Hills - Piccadilly Green construction site, inspection photo 1, 15 May 2016
  • Damac Hills - Piccadilly Green construction site, inspection photo 2, 15 May 2016
  • Damac Hills - Piccadilly Green construction site, inspection photo 3, 15 May 2016
  • Damac Hills - Piccadilly Green construction site, inspection photo 4, 15 May 2016

14 September 2015

43%+4.3 pts

  • Damac Hills - Piccadilly Green construction site, inspection photo 1, 14 September 2015
  • Damac Hills - Piccadilly Green construction site, inspection photo 2, 14 September 2015
  • Damac Hills - Piccadilly Green construction site, inspection photo 3, 14 September 2015
  • Damac Hills - Piccadilly Green construction site, inspection photo 4, 14 September 2015

21 May 2015

38%+16 pts

  • Damac Hills - Piccadilly Green construction site, inspection photo 1, 21 May 2015
  • Damac Hills - Piccadilly Green construction site, inspection photo 2, 21 May 2015
  • Damac Hills - Piccadilly Green construction site, inspection photo 3, 21 May 2015
  • Damac Hills - Piccadilly Green construction site, inspection photo 4, 21 May 2015

23 December 2014

22%+21 pts

  • Damac Hills - Piccadilly Green construction site, inspection photo 1, 23 December 2014
  • Damac Hills - Piccadilly Green construction site, inspection photo 2, 23 December 2014
  • Damac Hills - Piccadilly Green construction site, inspection photo 3, 23 December 2014
  • Damac Hills - Piccadilly Green construction site, inspection photo 4, 23 December 2014

28 May 2014

1.1%

  • Damac Hills - Piccadilly Green construction site, inspection photo 1, 28 May 2014
  • Damac Hills - Piccadilly Green construction site, inspection photo 2, 28 May 2014
  • Damac Hills - Piccadilly Green construction site, inspection photo 3, 28 May 2014
  • Damac Hills - Piccadilly Green construction site, inspection photo 4, 28 May 2014

All 71 site photos, by inspection date

Context

Damac Hills has 8 projects under construction, 38% built on average.

Damac Crescent Properties has 9 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Damac Hills - Piccadilly Green?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Damac Hills - Piccadilly Green handover date?
Construction of Damac Hills - Piccadilly Green is recorded as complete, with a registered completion date of February 2018. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Damac Hills - Piccadilly Green?
Damac Hills - Piccadilly Green was 100% built at the site inspection on 14 February 2018. The site has been inspected 10 times since May 2014. The Land Department took 71 site photos at its inspections.
Is Damac Hills - Piccadilly Green delayed?
The register lists construction as complete.
Who is building Damac Hills - Piccadilly Green?
The registered developer is Damac Crescent Properties. It has 9 other projects under construction in Dubai.
Which bank holds the escrow account for Damac Hills - Piccadilly Green?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.