Damac Hills - Piccadilly Green construction photos

71 photos from 10 site inspections, newest first. The percentage is how much of Damac Hills - Piccadilly Green was built on the day of each visit.

14 February 2018100% built

6 September 201798% built

23 May 201797% built

17 January 201787% built

7 November 201678% built

15 May 201651% built

14 September 201543% built

21 May 201538% built

23 December 201422% built

28 May 20141.1% built

Back to Damac Hills - Piccadilly Green construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.