Skip to content

Damac Hills- Pelham construction progress

The register lists Damac Hills- Pelham in Damac Hills as complete, with a registered completion date of July 2019. Its last site inspection on record was in August 2019. The developer is Damac Crescent Properties.

100%

Built, at the site inspection of 29 August 2019

Construction complete

Registered completion date
July 2019
Construction started
June 2014
First registered
January 2014
Community
Damac Hills
Units
173
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
دماك هيلز- بيلهام
Project number
1411
Site inspections
12

Schedule

The register lists Damac Hills- Pelham as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20152016201720182019
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

29 August 2019

100%+1.9 pts

  • Damac Hills- Pelham construction site, inspection photo 1, 29 August 2019
  • Damac Hills- Pelham construction site, inspection photo 2, 29 August 2019
  • Damac Hills- Pelham construction site, inspection photo 3, 29 August 2019
  • Damac Hills- Pelham construction site, inspection photo 4, 29 August 2019

14 November 2018

98%+3.3 pts

  • Damac Hills- Pelham construction site, inspection photo 1, 14 November 2018
  • Damac Hills- Pelham construction site, inspection photo 2, 14 November 2018
  • Damac Hills- Pelham construction site, inspection photo 3, 14 November 2018
  • Damac Hills- Pelham construction site, inspection photo 4, 14 November 2018

4 July 2018

95%+2.4 pts

  • Damac Hills- Pelham construction site, inspection photo 1, 4 July 2018
  • Damac Hills- Pelham construction site, inspection photo 2, 4 July 2018
  • Damac Hills- Pelham construction site, inspection photo 3, 4 July 2018
  • Damac Hills- Pelham construction site, inspection photo 4, 4 July 2018

15 February 2018

92%+0.7 pts

  • Damac Hills- Pelham construction site, inspection photo 1, 15 February 2018
  • Damac Hills- Pelham construction site, inspection photo 2, 15 February 2018
  • Damac Hills- Pelham construction site, inspection photo 3, 15 February 2018
  • Damac Hills- Pelham construction site, inspection photo 4, 15 February 2018

2 October 2017

92%+2.1 pts

  • Damac Hills- Pelham construction site, inspection photo 1, 2 October 2017
  • Damac Hills- Pelham construction site, inspection photo 2, 2 October 2017
  • Damac Hills- Pelham construction site, inspection photo 3, 2 October 2017
  • Damac Hills- Pelham construction site, inspection photo 4, 2 October 2017

19 June 2017

90%+8.4 pts

  • Damac Hills- Pelham construction site, inspection photo 1, 19 June 2017
  • Damac Hills- Pelham construction site, inspection photo 2, 19 June 2017
  • Damac Hills- Pelham construction site, inspection photo 3, 19 June 2017
  • Damac Hills- Pelham construction site, inspection photo 4, 19 June 2017

14 March 2017

81%+30 pts

  • Damac Hills- Pelham construction site, inspection photo 1, 14 March 2017
  • Damac Hills- Pelham construction site, inspection photo 2, 14 March 2017
  • Damac Hills- Pelham construction site, inspection photo 3, 14 March 2017
  • Damac Hills- Pelham construction site, inspection photo 4, 14 March 2017

21 December 2016

51%+21 pts

  • Damac Hills- Pelham construction site, inspection photo 1, 21 December 2016
  • Damac Hills- Pelham construction site, inspection photo 2, 21 December 2016
  • Damac Hills- Pelham construction site, inspection photo 3, 21 December 2016
  • Damac Hills- Pelham construction site, inspection photo 4, 21 December 2016

26 July 2016

31%+12 pts

  • Damac Hills- Pelham construction site, inspection photo 1, 26 July 2016
  • Damac Hills- Pelham construction site, inspection photo 2, 26 July 2016
  • Damac Hills- Pelham construction site, inspection photo 3, 26 July 2016
  • Damac Hills- Pelham construction site, inspection photo 4, 26 July 2016

15 March 2016

18%+7.4 pts

  • Damac Hills- Pelham construction site, inspection photo 1, 15 March 2016
  • Damac Hills- Pelham construction site, inspection photo 2, 15 March 2016
  • Damac Hills- Pelham construction site, inspection photo 3, 15 March 2016
  • Damac Hills- Pelham construction site, inspection photo 4, 15 March 2016

All 88 site photos, by inspection date

Context

Damac Hills has 8 projects under construction, 38% built on average.

Damac Crescent Properties has 9 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Damac Hills- Pelham?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Damac Hills- Pelham handover date?
Construction of Damac Hills- Pelham is recorded as complete, with a registered completion date of July 2019. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Damac Hills- Pelham?
Damac Hills- Pelham was 100% built at the site inspection on 29 August 2019. The site has been inspected 12 times since January 2015. The Land Department took 88 site photos at its inspections.
Is Damac Hills- Pelham delayed?
The register lists construction as complete.
Who is building Damac Hills- Pelham?
The registered developer is Damac Crescent Properties. It has 9 other projects under construction in Dubai.
Which bank holds the escrow account for Damac Hills- Pelham?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.