Damac Hills- Pelham construction photos

88 photos from 12 site inspections, newest first. The percentage is how much of Damac Hills- Pelham was built on the day of each visit.

29 August 2019100% built

14 November 201898% built

4 July 201895% built

15 February 201892% built

2 October 201792% built

19 June 201790% built

14 March 201781% built

21 December 201651% built

26 July 201631% built

15 March 201618% built

1 November 201511% built

13 January 20155.5% built

Back to Damac Hills- Pelham construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.