Damac Hills (2) - Violet 3 construction progress
The registered completion date for Damac Hills (2) - Violet 3 in Damac Hills 2 is June 2027. At the last site inspection, in May 2026, it was 36% built. The developer is Front Line Investment Management.
36%
Built, at the site inspection of 16 May 2026
Running behind its date
- Registered completion date
- June 2027
- Finish at recent pace
- January 2028
- Construction started
- December 2024
- First registered
- October 2024
- Developer
- Front Line Investment Management
- Community
- Damac Hills 2
- Units
- 616
- Escrow bank
- Dubai Islamic Bank
- Name in Arabic
- داماك هيلز (2) - فايليت 3
- Project number
- 3222
- Site inspections
- 4
Schedule
Between September 2025 and May 2026 the site added about 3.2 points a month. At that rate it would finish around January 2028, more than three months after its registered date of June 2027.
Site inspections
16 May 2026
36%+25 pts
18 September 2025
11%+8.9 pts
28 April 2025
1.9%+1.9 pts
5 August 2024
0%
Context
Damac Hills 2 has 12 projects under construction, 49% built on average.
Front Line Investment Management has 12 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in Damac Hills (2) - Violet 3?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Damac Hills (2) - Violet 3 handover date?
- The registered completion date is June 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around January 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Damac Hills (2) - Violet 3?
- Damac Hills (2) - Violet 3 was 36% built at the site inspection on 16 May 2026. The site has been inspected 4 times since August 2024. The Land Department took 22 site photos at its inspections.
- Is Damac Hills (2) - Violet 3 delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2027.
- Who is building Damac Hills (2) - Violet 3?
- The registered developer is Front Line Investment Management. It has 11 other projects under construction in Dubai.
- Which bank holds the escrow account for Damac Hills (2) - Violet 3?
- Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Damac Hills (2) - FarmhousesAlso by Front Line Investment Management. 83%, Due August 2025, passed.
- Damac Hills (2) - VioletAlso by Front Line Investment Management. 95%.
- Damac Hills (2) - NaturaAlso by Front Line Investment Management. 86%.
- Damac Hills (2) - Park Greens 3Also by Front Line Investment Management. 51%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.

.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)

.jpg&w=3840&q=75)
.jpg&w=3840&q=75)