Damac Hills (2) - Violet 2 construction progress

Damac Hills (2) - Violet 2 in Damac Hills 2 is 58% built at the Land Department inspection of September 2026. Developer Front Line Investment Management. Completion registered for February 2027.

58%

Built, at the Land Department site inspection of 22 September 2026

Running behind its date

Completion date (Land Department)
February 2027
Finish at recent pace
April 2028
Construction started
October 2024
Registered with the Land Department
October 2024
Community
Damac Hills 2
Units
223
Escrow bank
Dubai Islamic Bank
Name in Arabic
داماك هيلز (2) - فايليت 2
Land Department project number
3199
Land Department site inspections
5

Schedule

Between April 2026 and September 2026 the site added about 2.3 points a month. At that rate it would finish around April 2028, more than three months after the February 2027 date registered with the Land Department.

0%25%50%75%100%202520262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

22 September 2026

58%+13 pts

  • Damac Hills (2) - Violet 2 construction site, Land Department inspection photo 1, 22 September 2026
  • Damac Hills (2) - Violet 2 construction site, Land Department inspection photo 2, 22 September 2026
  • Damac Hills (2) - Violet 2 construction site, Land Department inspection photo 3, 22 September 2026
  • Damac Hills (2) - Violet 2 construction site, Land Department inspection photo 4, 22 September 2026

10 April 2026

45%+28 pts

  • Damac Hills (2) - Violet 2 construction site, Land Department inspection photo 1, 10 April 2026
  • Damac Hills (2) - Violet 2 construction site, Land Department inspection photo 2, 10 April 2026
  • Damac Hills (2) - Violet 2 construction site, Land Department inspection photo 3, 10 April 2026
  • Damac Hills (2) - Violet 2 construction site, Land Department inspection photo 4, 10 April 2026

18 August 2025

17%+13 pts

  • Damac Hills (2) - Violet 2 construction site, Land Department inspection photo 1, 18 August 2025
  • Damac Hills (2) - Violet 2 construction site, Land Department inspection photo 2, 18 August 2025
  • Damac Hills (2) - Violet 2 construction site, Land Department inspection photo 3, 18 August 2025
  • Damac Hills (2) - Violet 2 construction site, Land Department inspection photo 4, 18 August 2025

28 April 2025

3.9%+3.9 pts

  • Damac Hills (2) - Violet 2 construction site, Land Department inspection photo 1, 28 April 2025
  • Damac Hills (2) - Violet 2 construction site, Land Department inspection photo 2, 28 April 2025
  • Damac Hills (2) - Violet 2 construction site, Land Department inspection photo 3, 28 April 2025
  • Damac Hills (2) - Violet 2 construction site, Land Department inspection photo 4, 28 April 2025

25 July 2024

0%

  • Damac Hills (2) - Violet 2 construction site, Land Department inspection photo 1, 25 July 2024
  • Damac Hills (2) - Violet 2 construction site, Land Department inspection photo 2, 25 July 2024
  • Damac Hills (2) - Violet 2 construction site, Land Department inspection photo 3, 25 July 2024

All 33 site photos, by inspection date

Context

Damac Hills 2 has 12 projects under construction, 43% built on average.

Front Line Investment Management has 12 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Damac Hills (2) - Violet 2?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Damac Hills (2) - Violet 2 be completed?
The completion date registered with the Dubai Land Department is February 2027. At the pace of its recent inspections the site would reach 100% around April 2028. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Damac Hills (2) - Violet 2 is built?
58%, measured at the Land Department site inspection on 22 September 2026. The Land Department engineers have inspected the site 5 times since July 2024.
Is Damac Hills (2) - Violet 2 delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of February 2027.
Who is building Damac Hills (2) - Violet 2?
The registered developer is Front Line Investment Management. It has 11 other projects under construction in Dubai.
Which bank holds the escrow account for Damac Hills (2) - Violet 2?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.