Damac Hills (2) - Victoria 2 construction progress

The register lists Damac Hills (2) - Victoria 2 in Damac Hills 2 as complete, with a registered completion date of December 2024. Its last site inspection on record was in April 2025. The developer is Front Line Investment Management.

100%

Built, at the site inspection of 9 April 2025

Construction complete

Registered completion date
December 2024
Construction started
November 2021
First registered
September 2021
Community
Damac Hills 2
Units
96
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
داماك هيلز (2) - فيكتوريا 2
Project number
2293
Site inspections
7

Schedule

The register lists Damac Hills (2) - Victoria 2 as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2022202320242025
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

9 April 2025

100%+2.5 pts

  • Damac Hills (2) - Victoria 2 construction site, inspection photo 1, 9 April 2025
  • Damac Hills (2) - Victoria 2 construction site, inspection photo 2, 9 April 2025
  • Damac Hills (2) - Victoria 2 construction site, inspection photo 3, 9 April 2025
  • Damac Hills (2) - Victoria 2 construction site, inspection photo 4, 9 April 2025

28 October 2024

98%+36 pts

  • Damac Hills (2) - Victoria 2 construction site, inspection photo 1, 28 October 2024
  • Damac Hills (2) - Victoria 2 construction site, inspection photo 2, 28 October 2024
  • Damac Hills (2) - Victoria 2 construction site, inspection photo 3, 28 October 2024
  • Damac Hills (2) - Victoria 2 construction site, inspection photo 4, 28 October 2024

17 April 2024

61%+21 pts

  • Damac Hills (2) - Victoria 2 construction site, inspection photo 1, 17 April 2024
  • Damac Hills (2) - Victoria 2 construction site, inspection photo 2, 17 April 2024
  • Damac Hills (2) - Victoria 2 construction site, inspection photo 3, 17 April 2024
  • Damac Hills (2) - Victoria 2 construction site, inspection photo 4, 17 April 2024

8 November 2023

40%+23 pts

  • Damac Hills (2) - Victoria 2 construction site, inspection photo 1, 8 November 2023
  • Damac Hills (2) - Victoria 2 construction site, inspection photo 2, 8 November 2023
  • Damac Hills (2) - Victoria 2 construction site, inspection photo 3, 8 November 2023
  • Damac Hills (2) - Victoria 2 construction site, inspection photo 4, 8 November 2023

19 July 2023

17%+14 pts

  • Damac Hills (2) - Victoria 2 construction site, inspection photo 1, 19 July 2023
  • Damac Hills (2) - Victoria 2 construction site, inspection photo 2, 19 July 2023
  • Damac Hills (2) - Victoria 2 construction site, inspection photo 3, 19 July 2023
  • Damac Hills (2) - Victoria 2 construction site, inspection photo 4, 19 July 2023

20 February 2023

3.3%+0.1 pts

  • Damac Hills (2) - Victoria 2 construction site, inspection photo 1, 20 February 2023
  • Damac Hills (2) - Victoria 2 construction site, inspection photo 2, 20 February 2023
  • Damac Hills (2) - Victoria 2 construction site, inspection photo 3, 20 February 2023

3 October 2022

3.2%

  • Damac Hills (2) - Victoria 2 construction site, inspection photo 1, 3 October 2022
  • Damac Hills (2) - Victoria 2 construction site, inspection photo 2, 3 October 2022
  • Damac Hills (2) - Victoria 2 construction site, inspection photo 3, 3 October 2022
  • Damac Hills (2) - Victoria 2 construction site, inspection photo 4, 3 October 2022

All 40 site photos, by inspection date

Context

Damac Hills 2 has 12 projects under construction, 49% built on average.

Front Line Investment Management has 12 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Damac Hills (2) - Victoria 2?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Damac Hills (2) - Victoria 2 handover date?
Construction of Damac Hills (2) - Victoria 2 is recorded as complete, with a registered completion date of December 2024. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Damac Hills (2) - Victoria 2?
Damac Hills (2) - Victoria 2 was 100% built at the site inspection on 9 April 2025. The site has been inspected 7 times since October 2022. The Land Department took 40 site photos at its inspections.
Is Damac Hills (2) - Victoria 2 delayed?
The register lists construction as complete.
Who is building Damac Hills (2) - Victoria 2?
The registered developer is Front Line Investment Management. It has 12 other projects under construction in Dubai.
Which bank holds the escrow account for Damac Hills (2) - Victoria 2?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.