Damac Hills (2) - Park Greens 1 construction progress

The registered completion date for Damac Hills (2) - Park Greens 1 in Damac Hills 2 is March 2027. At the last site inspection, in October 2026, it was 39% built. The developer is Front Line Investment Management.

39%

Built, at the site inspection of 30 October 2026

Running behind its date

Registered completion date
March 2027
Finish at recent pace
June 2028
Construction started
February 2024
First registered
December 2023
Community
Damac Hills 2
Units
252
Escrow bank
First Abu Dhabi Bank
Name in Arabic
داماك هيلز (2) - بارك جرينز 1
Project number
2859
Site inspections
5

Schedule

Between May 2026 and October 2026 the site added about 3.1 points a month. At that rate it would finish around June 2028, more than three months after its registered date of March 2027.

0%25%50%75%100%2024202520262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

30 October 2026

39%+17 pts

  • Damac Hills (2) - Park Greens 1 construction site, inspection photo 1, 30 October 2026
  • Damac Hills (2) - Park Greens 1 construction site, inspection photo 2, 30 October 2026
  • Damac Hills (2) - Park Greens 1 construction site, inspection photo 3, 30 October 2026
  • Damac Hills (2) - Park Greens 1 construction site, inspection photo 4, 30 October 2026

13 May 2026

22%+18 pts

  • Damac Hills (2) - Park Greens 1 construction site, inspection photo 1, 13 May 2026
  • Damac Hills (2) - Park Greens 1 construction site, inspection photo 2, 13 May 2026
  • Damac Hills (2) - Park Greens 1 construction site, inspection photo 3, 13 May 2026
  • Damac Hills (2) - Park Greens 1 construction site, inspection photo 4, 13 May 2026

9 July 2025

3.5%+2.9 pts

  • Damac Hills (2) - Park Greens 1 construction site, inspection photo 1, 9 July 2025
  • Damac Hills (2) - Park Greens 1 construction site, inspection photo 2, 9 July 2025
  • Damac Hills (2) - Park Greens 1 construction site, inspection photo 3, 9 July 2025
  • Damac Hills (2) - Park Greens 1 construction site, inspection photo 4, 9 July 2025

5 July 2024

0.6%+0.6 pts

  • Damac Hills (2) - Park Greens 1 construction site, inspection photo 1, 5 July 2024
  • Damac Hills (2) - Park Greens 1 construction site, inspection photo 2, 5 July 2024

22 November 2023

0%

  • Damac Hills (2) - Park Greens 1 construction site, inspection photo 1, 22 November 2023
  • Damac Hills (2) - Park Greens 1 construction site, inspection photo 2, 22 November 2023
  • Damac Hills (2) - Park Greens 1 construction site, inspection photo 3, 22 November 2023

All 28 site photos, by inspection date

Context

Damac Hills 2 has 12 projects under construction, 49% built on average.

Front Line Investment Management has 12 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Damac Hills (2) - Park Greens 1?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Damac Hills (2) - Park Greens 1 handover date?
The registered completion date is March 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around June 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Damac Hills (2) - Park Greens 1?
Damac Hills (2) - Park Greens 1 was 39% built at the site inspection on 30 October 2026. The site has been inspected 5 times since November 2023. The Land Department took 28 site photos at its inspections.
Is Damac Hills (2) - Park Greens 1 delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2027.
Who is building Damac Hills (2) - Park Greens 1?
The registered developer is Front Line Investment Management. It has 11 other projects under construction in Dubai.
Which bank holds the escrow account for Damac Hills (2) - Park Greens 1?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.