Damac Hills (2) - Elo 2 & Elo 3 construction progress
The registered completion date for Damac Hills (2) - Elo 2 & Elo 3 in Damac Hills 2 is June 2027. At the last site inspection, in April 2026, it was 6.4% built. The developer is Front Line Investment Management.
6.4%
Built, at the site inspection of 15 April 2026
Running behind its date
- Registered completion date
- June 2027
- Finish at recent pace
- July 2040
- Construction started
- September 2024
- First registered
- August 2024
- Developer
- Front Line Investment Management
- Community
- Damac Hills 2
- Units
- 1,145
- Escrow bank
- Emirates NBD
- Name in Arabic
- داماك هيلز (2) - ايلو 2 و ايلو 3
- Project number
- 3122
- Site inspections
- 4
Schedule
Between April 2025 and April 2026 the site added about 0.5 points a month. At that rate it would finish around July 2040, more than three months after its registered date of June 2027.
Site inspections
15 April 2026
6.4%+4.9 pts
11 December 2025
1.5%+1.4 pts
30 April 2025
0.1%+0.1 pts
1 July 2024
0%
Context
Damac Hills 2 has 12 projects under construction, 49% built on average.
Front Line Investment Management has 12 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in Damac Hills (2) - Elo 2 & Elo 3?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Damac Hills (2) - Elo 2 & Elo 3 handover date?
- The registered completion date is June 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around July 2040. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Damac Hills (2) - Elo 2 & Elo 3?
- Damac Hills (2) - Elo 2 & Elo 3 was 6.4% built at the site inspection on 15 April 2026. The site has been inspected 4 times since July 2024. The Land Department took 17 site photos at its inspections.
- Is Damac Hills (2) - Elo 2 & Elo 3 delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2027.
- Who is building Damac Hills (2) - Elo 2 & Elo 3?
- The registered developer is Front Line Investment Management. It has 11 other projects under construction in Dubai.
- Which bank holds the escrow account for Damac Hills (2) - Elo 2 & Elo 3?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Damac Hills (2) - FarmhousesAlso by Front Line Investment Management. 83%, Due August 2025, passed.
- Damac Hills (2) - VioletAlso by Front Line Investment Management. 95%.
- Damac Hills (2) - NaturaAlso by Front Line Investment Management. 86%.
- Damac Hills (2) - Park Greens 3Also by Front Line Investment Management. 51%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.
.jpg&w=3840&q=75)




.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)