Skip to content

Damac Hills (2) - Elo 2 & Elo 3 construction progress

The registered completion date for Damac Hills (2) - Elo 2 & Elo 3 in Damac Hills 2 is June 2027. At the last site inspection, in April 2026, it was 6.4% built. The developer is Front Line Investment Management.

6.4%

Built, at the site inspection of 15 April 2026

Running behind its date

Registered completion date
June 2027
Finish at recent pace
July 2040
Construction started
September 2024
First registered
August 2024
Community
Damac Hills 2
Units
1,145
Escrow bank
Emirates NBD
Name in Arabic
داماك هيلز (2) - ايلو 2 و ايلو 3
Project number
3122
Site inspections
4

Schedule

Between April 2025 and April 2026 the site added about 0.5 points a month. At that rate it would finish around July 2040, more than three months after its registered date of June 2027.

0%25%50%75%100%202520262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

15 April 2026

6.4%+4.9 pts

  • Damac Hills (2) - Elo 2 & Elo 3 construction site, inspection photo 1, 15 April 2026
  • Damac Hills (2) - Elo 2 & Elo 3 construction site, inspection photo 2, 15 April 2026
  • Damac Hills (2) - Elo 2 & Elo 3 construction site, inspection photo 3, 15 April 2026
  • Damac Hills (2) - Elo 2 & Elo 3 construction site, inspection photo 4, 15 April 2026

11 December 2025

1.5%+1.4 pts

  • Damac Hills (2) - Elo 2 & Elo 3 construction site, inspection photo 1, 11 December 2025
  • Damac Hills (2) - Elo 2 & Elo 3 construction site, inspection photo 2, 11 December 2025
  • Damac Hills (2) - Elo 2 & Elo 3 construction site, inspection photo 3, 11 December 2025
  • Damac Hills (2) - Elo 2 & Elo 3 construction site, inspection photo 4, 11 December 2025

30 April 2025

0.1%+0.1 pts

  • Damac Hills (2) - Elo 2 & Elo 3 construction site, inspection photo 1, 30 April 2025
  • Damac Hills (2) - Elo 2 & Elo 3 construction site, inspection photo 2, 30 April 2025
  • Damac Hills (2) - Elo 2 & Elo 3 construction site, inspection photo 3, 30 April 2025
  • Damac Hills (2) - Elo 2 & Elo 3 construction site, inspection photo 4, 30 April 2025

1 July 2024

0%

  • Damac Hills (2) - Elo 2 & Elo 3 construction site, inspection photo 1, 1 July 2024
  • Damac Hills (2) - Elo 2 & Elo 3 construction site, inspection photo 2, 1 July 2024

All 17 site photos, by inspection date

Context

Damac Hills 2 has 12 projects under construction, 49% built on average.

Front Line Investment Management has 12 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Damac Hills (2) - Elo 2 & Elo 3?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Damac Hills (2) - Elo 2 & Elo 3 handover date?
The registered completion date is June 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around July 2040. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Damac Hills (2) - Elo 2 & Elo 3?
Damac Hills (2) - Elo 2 & Elo 3 was 6.4% built at the site inspection on 15 April 2026. The site has been inspected 4 times since July 2024. The Land Department took 17 site photos at its inspections.
Is Damac Hills (2) - Elo 2 & Elo 3 delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2027.
Who is building Damac Hills (2) - Elo 2 & Elo 3?
The registered developer is Front Line Investment Management. It has 11 other projects under construction in Dubai.
Which bank holds the escrow account for Damac Hills (2) - Elo 2 & Elo 3?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.