Damac Hills (2) - Elo 2 & Elo 3 construction progress

Damac Hills (2) - Elo 2 & Elo 3 in Damac Hills 2 is 6.4% built at the Land Department inspection of April 2026. Developer Front Line Investment Management. Completion registered for June 2027.

6.4%

Built, at the Land Department site inspection of 15 April 2026

Running behind its date

Completion date (Land Department)
June 2027
Finish at recent pace
July 2040
Construction started
September 2024
Registered with the Land Department
August 2024
Community
Damac Hills 2
Units
1,145
Escrow bank
Emirates NBD
Name in Arabic
داماك هيلز (2) - ايلو 2 و ايلو 3
Land Department project number
3122
Land Department site inspections
4

Schedule

Between April 2025 and April 2026 the site added about 0.5 points a month. At that rate it would finish around July 2040, more than three months after the June 2027 date registered with the Land Department.

0%25%50%75%100%202520262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

15 April 2026

6.4%+4.9 pts

  • Damac Hills (2) - Elo 2 & Elo 3 construction site, Land Department inspection photo 1, 15 April 2026
  • Damac Hills (2) - Elo 2 & Elo 3 construction site, Land Department inspection photo 2, 15 April 2026
  • Damac Hills (2) - Elo 2 & Elo 3 construction site, Land Department inspection photo 3, 15 April 2026
  • Damac Hills (2) - Elo 2 & Elo 3 construction site, Land Department inspection photo 4, 15 April 2026

11 December 2025

1.5%+1.4 pts

  • Damac Hills (2) - Elo 2 & Elo 3 construction site, Land Department inspection photo 1, 11 December 2025
  • Damac Hills (2) - Elo 2 & Elo 3 construction site, Land Department inspection photo 2, 11 December 2025
  • Damac Hills (2) - Elo 2 & Elo 3 construction site, Land Department inspection photo 3, 11 December 2025
  • Damac Hills (2) - Elo 2 & Elo 3 construction site, Land Department inspection photo 4, 11 December 2025

30 April 2025

0.1%+0.1 pts

  • Damac Hills (2) - Elo 2 & Elo 3 construction site, Land Department inspection photo 1, 30 April 2025
  • Damac Hills (2) - Elo 2 & Elo 3 construction site, Land Department inspection photo 2, 30 April 2025
  • Damac Hills (2) - Elo 2 & Elo 3 construction site, Land Department inspection photo 3, 30 April 2025
  • Damac Hills (2) - Elo 2 & Elo 3 construction site, Land Department inspection photo 4, 30 April 2025

1 July 2024

0%

  • Damac Hills (2) - Elo 2 & Elo 3 construction site, Land Department inspection photo 1, 1 July 2024
  • Damac Hills (2) - Elo 2 & Elo 3 construction site, Land Department inspection photo 2, 1 July 2024

All 17 site photos, by inspection date

Context

Damac Hills 2 has 12 projects under construction, 43% built on average. Damac Hills (2) - Elo 2 & Elo 3 is behind that average.

Front Line Investment Management has 12 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Damac Hills (2) - Elo 2 & Elo 3?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Track the handover

Questions

When will Damac Hills (2) - Elo 2 & Elo 3 be completed?
The completion date registered with the Dubai Land Department is June 2027. At the pace of its recent inspections the site would reach 100% around July 2040. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Damac Hills (2) - Elo 2 & Elo 3 is built?
6.4%, measured at the Land Department site inspection on 15 April 2026. The Land Department engineers have inspected the site 4 times since July 2024.
Is Damac Hills (2) - Elo 2 & Elo 3 delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2027.
Who is building Damac Hills (2) - Elo 2 & Elo 3?
The registered developer is Front Line Investment Management. It has 11 other projects under construction in Dubai.
Which bank holds the escrow account for Damac Hills (2) - Elo 2 & Elo 3?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.