Damac Hills (2) - Amazonia construction progress

The register lists Damac Hills (2) - Amazonia in Damac Hills 2 as complete, with a registered completion date of February 2021. Its last site inspection on record was in February 2021. The developer is Front Line Investment Management.

100%

Built, at the site inspection of 10 February 2021

Construction complete

Registered completion date
February 2021
Construction started
September 2015
First registered
April 2015
Community
Damac Hills 2
Units
198
Escrow bank
Abu Dhabi Islamic Bank
Name in Arabic
داماك هيلز (2) - أمازونيا
Project number
1648
Site inspections
12

Schedule

The register lists Damac Hills (2) - Amazonia as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%201620182020
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

10 February 2021

100%+0.5 pts

  • Damac Hills (2) - Amazonia construction site, inspection photo 1, 10 February 2021
  • Damac Hills (2) - Amazonia construction site, inspection photo 2, 10 February 2021
  • Damac Hills (2) - Amazonia construction site, inspection photo 3, 10 February 2021
  • Damac Hills (2) - Amazonia construction site, inspection photo 4, 10 February 2021

10 March 2020

100%+0.3 pts

  • Damac Hills (2) - Amazonia construction site, inspection photo 1, 10 March 2020
  • Damac Hills (2) - Amazonia construction site, inspection photo 2, 10 March 2020
  • Damac Hills (2) - Amazonia construction site, inspection photo 3, 10 March 2020
  • Damac Hills (2) - Amazonia construction site, inspection photo 4, 10 March 2020

26 August 2019

99%+2.0 pts

  • Damac Hills (2) - Amazonia construction site, inspection photo 1, 26 August 2019
  • Damac Hills (2) - Amazonia construction site, inspection photo 2, 26 August 2019
  • Damac Hills (2) - Amazonia construction site, inspection photo 3, 26 August 2019
  • Damac Hills (2) - Amazonia construction site, inspection photo 4, 26 August 2019

19 June 2019

97%+8.6 pts

  • Damac Hills (2) - Amazonia construction site, inspection photo 1, 19 June 2019
  • Damac Hills (2) - Amazonia construction site, inspection photo 2, 19 June 2019
  • Damac Hills (2) - Amazonia construction site, inspection photo 3, 19 June 2019
  • Damac Hills (2) - Amazonia construction site, inspection photo 4, 19 June 2019

20 January 2019

89%+5.9 pts

  • Damac Hills (2) - Amazonia construction site, inspection photo 1, 20 January 2019
  • Damac Hills (2) - Amazonia construction site, inspection photo 2, 20 January 2019
  • Damac Hills (2) - Amazonia construction site, inspection photo 3, 20 January 2019
  • Damac Hills (2) - Amazonia construction site, inspection photo 4, 20 January 2019

11 September 2018

83%+10 pts

  • Damac Hills (2) - Amazonia construction site, inspection photo 1, 11 September 2018
  • Damac Hills (2) - Amazonia construction site, inspection photo 2, 11 September 2018
  • Damac Hills (2) - Amazonia construction site, inspection photo 3, 11 September 2018
  • Damac Hills (2) - Amazonia construction site, inspection photo 4, 11 September 2018

29 March 2018

72%+12 pts

  • Damac Hills (2) - Amazonia construction site, inspection photo 1, 29 March 2018
  • Damac Hills (2) - Amazonia construction site, inspection photo 2, 29 March 2018
  • Damac Hills (2) - Amazonia construction site, inspection photo 3, 29 March 2018
  • Damac Hills (2) - Amazonia construction site, inspection photo 4, 29 March 2018

4 July 2017

60%+25 pts

  • Damac Hills (2) - Amazonia construction site, inspection photo 1, 4 July 2017
  • Damac Hills (2) - Amazonia construction site, inspection photo 2, 4 July 2017
  • Damac Hills (2) - Amazonia construction site, inspection photo 3, 4 July 2017
  • Damac Hills (2) - Amazonia construction site, inspection photo 4, 4 July 2017

1 March 2017

35%+24 pts

  • Damac Hills (2) - Amazonia construction site, inspection photo 1, 1 March 2017
  • Damac Hills (2) - Amazonia construction site, inspection photo 2, 1 March 2017
  • Damac Hills (2) - Amazonia construction site, inspection photo 3, 1 March 2017
  • Damac Hills (2) - Amazonia construction site, inspection photo 4, 1 March 2017

18 October 2016

11%+8.4 pts

  • Damac Hills (2) - Amazonia construction site, inspection photo 1, 18 October 2016
  • Damac Hills (2) - Amazonia construction site, inspection photo 2, 18 October 2016
  • Damac Hills (2) - Amazonia construction site, inspection photo 3, 18 October 2016
  • Damac Hills (2) - Amazonia construction site, inspection photo 4, 18 October 2016

All 91 site photos, by inspection date

Context

Damac Hills 2 has 12 projects under construction, 49% built on average.

Front Line Investment Management has 12 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Damac Hills (2) - Amazonia?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Damac Hills (2) - Amazonia handover date?
Construction of Damac Hills (2) - Amazonia is recorded as complete, with a registered completion date of February 2021. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Damac Hills (2) - Amazonia?
Damac Hills (2) - Amazonia was 100% built at the site inspection on 10 February 2021. The site has been inspected 12 times since October 2015. The Land Department took 91 site photos at its inspections.
Is Damac Hills (2) - Amazonia delayed?
The register lists construction as complete.
Who is building Damac Hills (2) - Amazonia?
The registered developer is Front Line Investment Management. It has 12 other projects under construction in Dubai.
Which bank holds the escrow account for Damac Hills (2) - Amazonia?
Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.