The One By Prestige One construction progress
The One By Prestige One in Barsha Heights is 7.0% built at the Land Department inspection of September 2026. Developer Prestige The One Real Estate Development. Completion registered for June 2027.
7.0%
Built, at the Land Department site inspection of 16 September 2026
Running behind its date
- Completion date (Land Department)
- June 2027
- Finish at recent pace
- June 2057
- Construction started
- January 2025
- Registered with the Land Department
- November 2024
- Developer
- Prestige The One Real Estate Development
- Community
- Barsha Heights
- Units
- 41
- Escrow bank
- Emirates NBD
- Name in Arabic
- ذا وان باي برست?ج وان
- Land Department project number
- 3332
- Land Department site inspections
- 5
Schedule
Between November 2025 and September 2026 the site added about 0.3 points a month. At that rate it would finish around June 2057, more than three months after the June 2027 date registered with the Land Department.
Site inspections
16 September 2026
7.0%+0.5 pts
11 June 2026
6.5%+2.0 pts
25 November 2025
4.6%+3.5 pts
15 August 2025
1.1%+1.1 pts
15 October 2024
0%
Context
Barsha Heights has 2 projects under construction, 4.8% built on average.
Own a unit in The One By Prestige One?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will The One By Prestige One be completed?
- The completion date registered with the Dubai Land Department is June 2027. At the pace of its recent inspections the site would reach 100% around June 2057. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of The One By Prestige One is built?
- 7.0%, measured at the Land Department site inspection on 16 September 2026. The Land Department engineers have inspected the site 5 times since October 2024.
- Is The One By Prestige One delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2027.
- Who is building The One By Prestige One?
- The registered developer is Prestige The One Real Estate Development.
- Which bank holds the escrow account for The One By Prestige One?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.





.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)