The One By Prestige One construction progress
The registered completion date for The One By Prestige One in Barsha Heights is June 2027. At the last site inspection, in September 2026, it was 7.0% built. The developer is Prestige The One Real Estate Development.
7.0%
Built, at the site inspection of 16 September 2026
Running behind its date
- Registered completion date
- June 2027
- Finish at recent pace
- June 2057
- Construction started
- January 2025
- First registered
- November 2024
- Developer
- Prestige The One Real Estate Development
- Community
- Barsha Heights
- Units
- 41
- Escrow bank
- Emirates NBD
- Name in Arabic
- ذا وان باي برست?ج وان
- Project number
- 3332
- Site inspections
- 5
Schedule
Between November 2025 and September 2026 the site added about 0.3 points a month. At that rate it would finish around June 2057, more than three months after its registered date of June 2027.
Site inspections
16 September 2026
7.0%+0.5 pts
11 June 2026
6.5%+2.0 pts
25 November 2025
4.6%+3.5 pts
15 August 2025
1.1%+1.1 pts
15 October 2024
0%
Context
Barsha Heights has 2 projects under construction, 4.8% built on average.
Own a unit in The One By Prestige One?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the The One By Prestige One handover date?
- The registered completion date is June 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around June 2057. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on The One By Prestige One?
- The One By Prestige One was 7.0% built at the site inspection on 16 September 2026. The site has been inspected 5 times since October 2024. The Land Department took 18 site photos at its inspections.
- Is The One By Prestige One delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2027.
- Who is building The One By Prestige One?
- The registered developer is Prestige The One Real Estate Development.
- Which bank holds the escrow account for The One By Prestige One?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- The Chedi Private ResidencesNearby in Barsha Heights. 2.6%, Due February 2029.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.




.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)