Paradise Hills construction photos
177 photos taken by Dubai Land Department engineers at 22 site inspections, newest first. The percentage is how much of Paradise Hills was built on the day of each visit.
10 September 202684% built
5 August 202684% built
3 February 202684% built
7 July 202583% built
9 October 202480% built
15 February 202460% built
3 August 202350% built
29 December 202245% built
20 October 202241% built
30 May 202239% built
5 December 202138% built
11 March 202138% built
17 May 202038% built
2 September 201916% built
16 July 201914% built
14 March 20199.7% built
10 December 20172.9% built
20 June 20172.8% built
19 December 20162.8% built
28 July 20162.0% built
31 March 20160% built
19 May 20150% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.