Skip to content

When the developer cancels, and how much it can keep.

Dubai lets a developer end an off-plan sale when the buyer stops paying, through a fixed procedure at the Land Department. What it keeps depends on how far the building has got. For buyers who have fallen behind, or who think the developer has.

Updated

A Dubai developer can end an off-plan sale when the buyer stops paying, and it has to go through the Land Department to do it. The Department serves a 30-day notice first. If you still haven't paid, the project's completion percentage sets what the developer may keep: up to 25% of the price below 60% built, and up to 40% from 60% to 80%. Above 80% it can hold you to the full price.

In short

  • The rule is Article 11 of Law 13 of 2008, in the wording Law 19 of 2020 gave it. A termination that doesn't follow its steps is void.

  • Nothing can be cancelled until the Land Department has served a 30-day notice and that time has run out.

  • The cap is a share of the unit's price. If you've paid less than the cap, you can lose everything paid so far.

  • On 23 November 2026, 1,271 of the 1,577 active projects on the register were below 60% complete, the bracket where the cap is 25%.

The law behind it

It all sits in Article 11 of Law No. 13 of 2008. That law set up the interim register, where an off-plan sale is recorded until the building is finished and a title deed exists. The article has been rewritten three times. In its first form a developer could keep up to 30% of whatever the buyer had paid. Law No. 9 of 2009 swapped that for brackets based on construction progress, Law No. 19 of 2017 rewrote the procedure, and the text in force now came with Law No. 19 of 2020, issued on 24 November that year.

Plenty of older articles still quote the 2017 version, so one change is worth knowing. Until 2020, a developer that hadn't started building could keep 30% of what had been paid. That's gone. If work hasn't begun for reasons outside the developer's control, today's text makes it refund every payment.

Two further lines matter to a buyer. The rules count as public order, so anything done without following them is void. And none of it stops you going to court or to arbitration.

Before anything is cancelled

A developer can't just write to say the deal is off. The law sets four steps, and the Land Department runs the middle two.

  • The developer reports you.

    It files the Department's form with both parties' details, the unit, and a detailed account of the obligations you've missed.

  • The Department gives you 30 days.

    Once it has checked the breach, it sends you a written, dated notice to pay, by hand, registered mail, email or another channel it sets. Where it can, it also tries to broker a settlement, which becomes an addendum to your sale agreement.

  • It certifies the percentage.

    If the 30 days pass with no payment and no settlement, the Department issues the developer an official document. It confirms the procedure was followed and states the project's completion percentage, calculated under RERA's rules.

  • The developer acts on the bracket.

    With that document it can apply the bracket without going to court or arbitration. At the Land Department this is the service called termination of initial registration, which costs the developer AED 620.

What the Department checks before it lets a termination through

Its conditions for that service say the sale must have been made before the project was completed, and that you received the developer's warning, or refused it, at least a month earlier and still didn't pay. The amount in the warning has to match the Department's own notice. It can only cover instalments of the price, too. Late fines, registration fees, service fees and admin charges aren't allowed in it. If the notice can't be delivered to the addresses in your contract, it gets published instead, in Arabic and English.

The 30 days are the part you control. Start with the amount. If your plan is linked to construction stages, an instalment isn't due until the project consultant confirms the stage has been reached, which our guide to checking an off-plan project's progress explains. If the claim stands and you can't pay it, try the settlement route. Whatever revised plan you agree there becomes part of the contract and binds the developer as much as you. You can also sell the unit on, which Article 6 of the same law allows, provided a buyer turns up in time.

What the developer can keep

What Article 11 lets a developer do once the notice has expired
Project completionWhat the developer may doWhen the rest comes back
Above 80%Keep the contract and what you've paid, and claim the balance; or ask the Land Department to auction the unit, at your cost; or terminate and keep up to 40% of the priceIf it terminates: within a year, or 60 days after resale if sooner
60% to 80%Terminate and keep up to 40% of the priceWithin a year, or 60 days after resale if sooner
Started, under 60%Terminate and keep up to 25% of the priceWithin a year, or 60 days after resale if sooner
Not started, for reasons outside the developer's controlRefund every paymentUnder the escrow law, Law No. 8 of 2007
Cancelled by a final RERA decisionRefund every paymentUnder the escrow law, Law No. 8 of 2007

Article 11 of Law No. 13 of 2008 as superseded by Law No. 19 of 2020, Dubai Legislation Portal, read 23 November 2026. The caps are shares of the unit's price in the contract. The English text is a translation; the Arabic prevails.

Those caps are a share of the unit's price, and the developer keeps at most that much out of what you've paid. Say you bought a flat for AED 1,500,000 and have paid 35%, which is AED 525,000. With the project 45% built, the cap is 25%, or AED 375,000, so AED 150,000 comes back to you. If it's 70% built the cap becomes AED 600,000. That's more than you paid, and you get nothing back. Article 11 gives the developer no claim for the difference, though.

Above 80% the developer has choices the other brackets don't give it. It can keep the sale alive and pursue the AED 975,000 still owed in that example, or have the Department sell the unit at public auction to recover it and charge you the costs of the sale. The percentages are ceilings, and a developer is free to settle for less.

Where projects stand today

The bracket turns on the completion percentage, and the Land Department publishes one for every project under construction. On 23 November 2026 we sorted all 1,577 active projects on its register by the Article 11 bracket they currently fall in.

Dubai's active off-plan projects by Article 11 bracket
Completion on the registerProjectsUnits
Above 80%13943,628
60% to 80%16743,707
Above 0%, under 60%1,052343,889
0%21968,679
All active projects1,577499,903

Dubai Land Department Mashrooi register, read 23 November 2026. All 1,577 projects listed as active, by the completion percentage from their latest recorded inspection. Units as registered.

About four projects in five, 1,271 of them, are under 60%. In that range the most a developer can keep after terminating is a quarter of the price. Only 139 have passed 80%, the one bracket where it can insist on the full price instead.

Read the 0% row with care. In the law, a project has started once the developer has taken over the site and begun work under approved plans, and a register figure of 0% doesn't answer that by itself. For 176 of those 219 projects, the start date on the register has already passed.

The register gives the figure at the latest inspection, so look at when that was. The percentage that decides a termination is the one the Department certifies when the notice runs out, and it may be newer. You can find your own project on our off-plan tracker, with its last inspection, the date and the site photos.

When the developer is the one at fault

Article 11 is written for a buyer who stops paying. Turn it round and there's no matching procedure. The Land Department says it can't terminate a contract between a developer and a buyer at the buyer's request. It will try to reconcile the two of you, and past that point a buyer who wants out goes to the real estate court.

The obvious case is a late handover. Whether a delay lets you end the contract depends on what your sale agreement says, and in the end on the court. Registered completion dates also move, because RERA asks developers to update them as projects change.

Sometimes the money comes back under the law itself. Article 11 says that if the developer hasn't started work for reasons outside its control, or RERA has cancelled the project by a final decision, every payment is refunded under the escrow law. A cancellation hands the escrow balance to the Department's liquidation section, and our progress guide covers how that repays buyers. It isn't quick. The Department says reaching a cancellation decision takes at least three months, and liquidation has no fixed timetable.

RERA can start cancellation on a stalled project with very little built, and on 23 November, 535 active projects stood at 5% or less. A low figure on its own doesn't prove a stall, so check the inspection date and the photos as well.

Article 11 as set by Law No. 19 of 2020 and read on the Dubai Legislation Portal, with the Land Department's termination service page and its published answers on cancelled projects, all read 23 November 2026. The English texts are translations and the Arabic prevails. Not legal advice. If a notice arrives, have a lawyer read your sale agreement before the 30 days are up.

Questions

Can a developer cancel my off-plan contract in Dubai?

Yes, if you've stopped paying and the Land Department's procedure has run its course. The developer reports the breach, the Department gives you 30 days' written notice, and if you haven't paid or settled by the end of it, the Department certifies the project's completion percentage. Only then can the developer terminate, and a termination that skips any of those steps is void.

How much can a developer keep if I cancel off plan in Dubai?

It turns on how far the building has got. Where work has started but the project is under 60% complete, the developer can keep up to 25% of the contract price. From 60% to 80% the cap is 40%. It keeps that much at most from what you've paid and returns the rest within a year of termination, or within 60 days of reselling the unit if that comes sooner. A cancellation you agree with the developer is a separate thing, and then the terms are whatever you both sign.

What is Article 11 of Law 13 of 2008?

Dubai's rule for a buyer who stops paying for an off-plan unit. Law 9 of 2009 tied it to construction progress, and the version in force now comes from Law 19 of 2020. It sets out the notice procedure, the brackets for what a developer may keep, and full refunds where work never started or RERA cancels the project.

How long does the developer have to refund me after termination?

One year from the termination, or 60 days from the day the unit is resold to someone else, whichever is earlier. That's for terminations where the developer keeps a share of the price. Refunds on a project that never started, or that RERA cancelled, go through the escrow law instead. After a cancellation the developer is asked to pay within 60 days of the decision, and RERA can extend that.

Can I cancel my off-plan contract if the developer is delayed?

Not through the Land Department. It has no power to end a contract at a buyer's request, though it will try to reconcile you with the developer. To end it on your own terms you go to the real estate court, or to arbitration if your contract provides for it, and the delay clauses in your sale agreement will carry most of the weight.

What happens if the developer never starts building?

If it hasn't started for reasons outside its control, Article 11 requires it to refund everything buyers paid, under the escrow law. Before 2020 it could keep 30%; Law 19 of 2020 took that away. A stalled project can also be cancelled by RERA, in which case the Land Department's liquidation section repays buyers from the escrow account, in full or pro rata.
An unfinished floor inside a Dubai tower, bare concrete columns, blockwork walls and scaffolding under exposed ducts

Mulki checks every inspection on your project, before the next instalment falls due.