Palmarosa construction photos

143 photos taken by Dubai Land Department engineers at 16 site inspections, newest first. The percentage is how much of Palmarosa was built on the day of each visit.

8 January 202698% built

15 May 202497% built

6 November 202395% built

18 August 202294% built

7 February 202293% built

24 October 202192% built

10 November 202092% built

26 March 202089% built

24 October 201988% built

1 July 201887% built

18 July 201777% built

10 November 201670% built

26 May 201664% built

5 January 201558% built

7 October 201321% built

4 February 201315% built

Back to Palmarosa construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.