Palmarosa construction progress
Palmarosa in The Palmarosa was registered to complete in October 2022 and is still under construction. At the last site inspection, in January 2026, it was 98% built. The developer is Gulf Developers.
98%
Built, at the site inspection of 8 January 2026
49 months past its registered completion date
- Registered completion date
- October 2022
- Finish at recent pace
- April 2029
- Construction started
- October 2008
- First registered
- November 2008
- Developer
- Gulf Developers
- Community
- The Palmarosa
- Units
- 316
- Escrow bank
- Dubai Islamic Bank
- Name in Arabic
- بالماروسا
- Project number
- 158
- Site inspections
- 16
Schedule
Palmarosa was registered to complete in October 2022, 49 months ago, and is still under construction. Over the last year of inspections it has added about 0.1 points a month. Kept at that rate, the site would reach 100% around April 2029.
Site inspections
8 January 2026
98%+1.1 pts
15 May 2024
97%+1.6 pts
6 November 2023
95%+1.0 pts
18 August 2022
94%+0.8 pts
7 February 2022
93%+1.3 pts
24 October 2021
92%
10 November 2020
92%+2.9 pts
26 March 2020
89%+0.9 pts
24 October 2019
88%+1.0 pts
1 July 2018
87%+11 pts
Context
Own a unit in Palmarosa?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Palmarosa handover date?
- The registered completion date was October 2022, and the register still lists Palmarosa as under construction. At the pace of its recent inspections the site would reach 100% around April 2029. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Palmarosa?
- Palmarosa was 98% built at the site inspection on 8 January 2026. The site has been inspected 16 times since February 2013. The Land Department took 143 site photos at its inspections.
- Is Palmarosa delayed?
- Yes. Its registered completion date of October 2022 has passed and the project is still listed as under construction.
- Who is building Palmarosa?
- The registered developer is Gulf Developers.
- Which bank holds the escrow account for Palmarosa?
- Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.