Palmarosa construction progress
Palmarosa in The Palmarosa is 98% built at the Land Department inspection of January 2026. Developer Gulf Developers. Completion registered for October 2022.
98%
Built, at the Land Department site inspection of 8 January 2026
47 months past its registered completion date
- Completion date (Land Department)
- October 2022
- Finish at recent pace
- April 2029
- Construction started
- October 2008
- Registered with the Land Department
- November 2008
- Developer
- Gulf Developers
- Community
- The Palmarosa
- Units
- 316
- Escrow bank
- Dubai Islamic Bank
- Name in Arabic
- بالماروسا
- Land Department project number
- 158
- Land Department site inspections
- 16
Schedule
Palmarosa was registered to complete in October 2022, 47 months ago, and is still under construction. Over the last year of inspections it has added about 0.1 points a month. Kept at that rate, the site would reach 100% around April 2029.
Site inspections
8 January 2026
98%+1.1 pts
15 May 2024
97%+1.6 pts
6 November 2023
95%+1.0 pts
18 August 2022
94%+0.8 pts
7 February 2022
93%+1.3 pts
24 October 2021
92%
10 November 2020
92%+2.9 pts
26 March 2020
89%+0.9 pts
24 October 2019
88%+1.0 pts
1 July 2018
87%+11 pts
Context
Own a unit in Palmarosa?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Track the handoverQuestions
- When will Palmarosa be completed?
- The completion date registered with the Dubai Land Department is October 2022. At the pace of its recent inspections the site would reach 100% around April 2029. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Palmarosa is built?
- 98%, measured at the Land Department site inspection on 8 January 2026. The Land Department engineers have inspected the site 16 times since February 2013.
- Is Palmarosa delayed?
- Yes. Its registered completion date of October 2022 has passed and the Land Department still lists it as under construction.
- Who is building Palmarosa?
- The registered developer is Gulf Developers.
- Which bank holds the escrow account for Palmarosa?
- Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.


.jpeg&w=3840&q=75)





.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)

.jpg&w=3840&q=75)

.jpg&w=3840&q=75)

.jpg&w=3840&q=75)
.jpg&w=3840&q=75)