Palmarosa construction progress

Palmarosa in The Palmarosa is 98% built at the Land Department inspection of January 2026. Developer Gulf Developers. Completion registered for October 2022.

98%

Built, at the Land Department site inspection of 8 January 2026

47 months past its registered completion date

Completion date (Land Department)
October 2022
Finish at recent pace
April 2029
Construction started
October 2008
Registered with the Land Department
November 2008
Developer
Gulf Developers
Community
The Palmarosa
Units
316
Escrow bank
Dubai Islamic Bank
Name in Arabic
بالماروسا
Land Department project number
158
Land Department site inspections
16

Schedule

Palmarosa was registered to complete in October 2022, 47 months ago, and is still under construction. Over the last year of inspections it has added about 0.1 points a month. Kept at that rate, the site would reach 100% around April 2029.

0%25%50%75%100%20092013201720212025
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

8 January 2026

98%+1.1 pts

  • Palmarosa construction site, Land Department inspection photo 1, 8 January 2026
  • Palmarosa construction site, Land Department inspection photo 2, 8 January 2026
  • Palmarosa construction site, Land Department inspection photo 3, 8 January 2026
  • Palmarosa construction site, Land Department inspection photo 4, 8 January 2026

15 May 2024

97%+1.6 pts

  • Palmarosa construction site, Land Department inspection photo 1, 15 May 2024
  • Palmarosa construction site, Land Department inspection photo 2, 15 May 2024
  • Palmarosa construction site, Land Department inspection photo 3, 15 May 2024
  • Palmarosa construction site, Land Department inspection photo 4, 15 May 2024

6 November 2023

95%+1.0 pts

  • Palmarosa construction site, Land Department inspection photo 1, 6 November 2023
  • Palmarosa construction site, Land Department inspection photo 2, 6 November 2023
  • Palmarosa construction site, Land Department inspection photo 3, 6 November 2023
  • Palmarosa construction site, Land Department inspection photo 4, 6 November 2023

18 August 2022

94%+0.8 pts

  • Palmarosa construction site, Land Department inspection photo 1, 18 August 2022
  • Palmarosa construction site, Land Department inspection photo 2, 18 August 2022
  • Palmarosa construction site, Land Department inspection photo 3, 18 August 2022
  • Palmarosa construction site, Land Department inspection photo 4, 18 August 2022

7 February 2022

93%+1.3 pts

  • Palmarosa construction site, Land Department inspection photo 1, 7 February 2022
  • Palmarosa construction site, Land Department inspection photo 2, 7 February 2022
  • Palmarosa construction site, Land Department inspection photo 3, 7 February 2022
  • Palmarosa construction site, Land Department inspection photo 4, 7 February 2022

24 October 2021

92%

  • Palmarosa construction site, Land Department inspection photo 1, 24 October 2021
  • Palmarosa construction site, Land Department inspection photo 2, 24 October 2021
  • Palmarosa construction site, Land Department inspection photo 3, 24 October 2021
  • Palmarosa construction site, Land Department inspection photo 4, 24 October 2021

10 November 2020

92%+2.9 pts

  • Palmarosa construction site, Land Department inspection photo 1, 10 November 2020
  • Palmarosa construction site, Land Department inspection photo 2, 10 November 2020
  • Palmarosa construction site, Land Department inspection photo 3, 10 November 2020
  • Palmarosa construction site, Land Department inspection photo 4, 10 November 2020

26 March 2020

89%+0.9 pts

  • Palmarosa construction site, Land Department inspection photo 1, 26 March 2020
  • Palmarosa construction site, Land Department inspection photo 2, 26 March 2020
  • Palmarosa construction site, Land Department inspection photo 3, 26 March 2020
  • Palmarosa construction site, Land Department inspection photo 4, 26 March 2020

24 October 2019

88%+1.0 pts

  • Palmarosa construction site, Land Department inspection photo 1, 24 October 2019
  • Palmarosa construction site, Land Department inspection photo 2, 24 October 2019
  • Palmarosa construction site, Land Department inspection photo 3, 24 October 2019
  • Palmarosa construction site, Land Department inspection photo 4, 24 October 2019

1 July 2018

87%+11 pts

  • Palmarosa construction site, Land Department inspection photo 1, 1 July 2018
  • Palmarosa construction site, Land Department inspection photo 2, 1 July 2018
  • Palmarosa construction site, Land Department inspection photo 3, 1 July 2018
  • Palmarosa construction site, Land Department inspection photo 4, 1 July 2018

All 143 site photos, by inspection date

Context

Own a unit in Palmarosa?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Track the handover

Questions

When will Palmarosa be completed?
The completion date registered with the Dubai Land Department is October 2022. At the pace of its recent inspections the site would reach 100% around April 2029. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Palmarosa is built?
98%, measured at the Land Department site inspection on 8 January 2026. The Land Department engineers have inspected the site 16 times since February 2013.
Is Palmarosa delayed?
Yes. Its registered completion date of October 2022 has passed and the Land Department still lists it as under construction.
Who is building Palmarosa?
The registered developer is Gulf Developers.
Which bank holds the escrow account for Palmarosa?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.